5
Verify that the SFP is seated properly.
6
Remove any endcaps from the ports.
To remove an SFP end cap:
■
Grasp the top and bottom of an end cap.
■
Pull the end cap straight back. Do not twist the end cap.
■
Keep the end caps in a dust-free location in case you need them at another
time.
Connecting the Velocity 7330 compute node to
the Primary Storage Shelf
The compute node ships with four, 1 meter, Fibre Channel (FC) cables. FC cables
connect the compute node to the Primary Storage Shelf canisters. To ensure
communication redundancy, c
onnect the units exactly as described in this topic.
The following diagrams and tables show the locations of the FC ports on both
components.
Slot 1
FC
Slot 2
Slot 3
Slot 4
Slot 5
Slot 6
FC
2 1
2 1
41
Installation procedures
Connecting the Velocity 7330 compute node to the Primary Storage Shelf