Place one thumb on each of the two pads that are shown by the red arrows.
7
Push the carrier forward towards the rear of the slot, in the direction of the
circled end of the carrier.
The release latch clicks into place.
8
Locate slot 15 on the left side of the second row. Slot 15 is to the right of slot
14. Install blanks into slots 15 through 27.
9
Locate slot 29, to the right of slot 28.
10
Install blanks into slots 29 to 41.
11
If you need to remove a blank, slide the release latch to the right. The blank
pops up.
12
Verify that all slots are filled.
13
Push the drawer into the shelf by pressing the two drawer release buttons
located (one per side) on the side of the drawer to close the drawer until the
latches click.
14
Engage the anti-tamper locks as needed.
Installing the compute node rack rails
Veritas recommends the following.
■
The compute node requires two RUs of space
■
Two people should install the rails; one person at the back of the rack and one
at the front.
■
Two people should lift and place the compute node into the mounted rails.
49
Hardware installation procedures
Installing the compute node rack rails