See
on page 26.
The following describes the necessary personnel and equipment that are needed
at the installation site:
■
At least two people or a mechanical lift to move the appliance and the storage
shelves.
■
Cables to connect the appliance to your corporate network.
■
A USB-keyboard and a monitor to connect to the appliance.
■
A 19-inch rack with dual Power Distribution Units (PDUs) with 120VAC or
220VAC power supplies for the compute node.
■
A magnetic Philips-head screw driver to install the storage shelf rails into the
rack.
■
A screwdriver with a 2mm Hex bit to secure the bezels to the front of each
storage shelf drawer.
■
A 19-inch rack with dual Power Distribution Units (PDUs) with 220VAC power
input for the storage shelves.
See
“Best practices for rack installation”
on page 25.
Appliance shipping container contents
The appliance and each storage shelf are shipped in separate containers. Each
container includes other boxes and contents. The disk drives are installed into the
appliance and the storage shelf at the factory.
The following items ship within the appliance box.
■
Open Me First container, containing:
■
Deployment plan that provides basic information, and links to detailed
information
■
Cable straps
■
Quick Installation card
■
Cable connections poster
■
Envelope containing the following:
■
Warranty and license information
■
Accessory box containing rack rails
■
Two power cables
■
Bezel
22
Preinstallation requirements
Appliance shipping container contents