9.0
Commissioning
Note:
This equipment should not be put into use until it has been commissioned by a
competent person in accordance with the instructions contained within this manual,
and any local regulations. Carbolite Gero offer an installation and commissioning
service. Please contact Carbolite Gero Service for details.
9.1
Pre-Commissioning
When the product is cold and disconnected from the power
supply, visually check the following:
Checked by:
Siting /
Securing
Check that the product is placed on a secure, level
surface and cannot topple over.
Packaging
Check that all packaging material has been removed
from inside and around the product.
General
Condition
Check that no damage has occurred during delivery
and siting.
Panels
Check that all covers and access panels are securely
fitted.
General Access
Check that there is sufficient clearance around the
top and all sides of the product.
Electrical Supply
l
Check that the voltage stated on the product rat-
ing label matches the electrical supply of the
installation site.
l
Check that all electrical supply cables are
securely attached to/ plugged into the product.
Earth
Connection
Check that an earth connection has been made. The
control cabinet and all removable panels on the
furnace should be earthed.
Rating Label /
Warning Labels
Check that all labels are fitted and all information is
legible.
20