C: Standard Piping Installation Requirements
Observe the following requirements when installing the boiler piping:
1) Relief Valve (Required) – The relief valve is shipped loose and must be installed in the location shown in Figure
9.6, using the side outlet Tee and other fittings provided. ASME Section IV currently requires that this relief
valve be installed above the heat exchanger as shown. Pipe the outlet of the relief valve to a location where water
or steam will not create a hazard or cause property damage if the valve opens. The end of the discharge pipe must
terminate in unthreaded pipe. If the relief valve discharge is not piped to a drain, it must terminate at least 6” above
the floor. Do not run the discharge piping through an area that is prone to freezing. The termination of the relief
valve must be in an area where it is not likely to become plugged by debris.
The relief valve supplied with the boiler is set to open at 30 psi. If it is replaced, the replacement must have
a setting less than or equal to the maximum allowable working pressure (MAWP) shown on the ASME data plate.
2) Gauge (Required) - Indicates supply water pressure and temperature. This gauge is shipped loose. Install it as shown
in Figure 9.6.
3) Circulator (required) – The boiler loop circulator is supplied by the installer and must be sized to provide the
required boiler flow rate. Usually at least one additional circulator will be required for the system to work properly.
See the previous section for more information.
4) Expansion Tank (required) –
If this boiler is replacing an existing boiler with no other changes in the system,
the old expansion tank can generally be reused. If the expansion tank must be replaced, consult the expansion tank
manufacturer’s literature for proper sizing.
5) Fill Valve (required) – Either a manual or automatic fill valve may be used, but a manual valve is preferred because
it eliminates unmonitored additions of make-up water to the system. The ideal location for the fill valve is at the
expansion
tank.
6) Automatic Air Vent (required) – At least one automatic air vent is required. Manual air vents will usually be required
in other parts of the system to remove air during initial fill.
7) Manual Reset High Limit (required by some codes) - This control is required by ASME CSD-1 and some
other codes. Install the high limit in the boiler supply piping just above the boiler with no intervening valves. Set
the manual reset high limit to 200°F. Wire the limit per Figure 10.3 in the Wiring section.
8) Isolation Valves (recommended) - Isolation valves are useful when the boiler must be drained, as they will eliminate
having to drain and refill the entire system.
9) Strainer (recommended) – Install a Y Strainer, or other suitable strainer, to prevent any system debris from entering
the boiler and fouling the water passages. Note that some strainers have a significant pressure drop, which may
impact the ability of the boiler pump to obtain the required flow. See section B for additional information.
10) Drain Valve (required) – Install the drain valve supplied as shown in Figure 9.6.
DANGER
Explosion / Scald Hazard
Pipe relief valve discharge to a location where the potential of severe burns is eliminated.
Do not install a relief valve having a setting greater than the MAWP shown on the rating
plate.
Do not install a valve in the relief valve discharge line.
Do not install relief valve in a location other than that specified by the factory.
Do not plug the relief valve discharge.
Summary of Contents for Shadow Series
Page 10: ...9 Figure 5 1 Wall Layout Mounting Hole Location...
Page 11: ...10 Figure 5 2 Boiler Mounting Bracket Installation Boiler Wall Mounting...
Page 17: ...16 FIGURE 7 4 WALL PENETRATION CLEARANCES FOR PVC VENT PIPE...
Page 34: ...33 FIGURE 7 24 INSTALLATION OF IPEX AND DIVERSITECH CONCENTRIC TERMINAL THROUGH ROOF...
Page 41: ...40 FIGURE 9 2 NEAR BOILER PIPING HEATING ONLY BOILER LOOP PIPING SHOWN SHADED...
Page 42: ...41 FIGURE 9 3a NEAR BOILER PIPING HEATING PLUS INDIRECT WATER HEATER...
Page 43: ...42 FIGURE 9 3b NEAR BOILER PIPING HEATING PLUS INDIRECT WATER HEATER...
Page 47: ...46 This page is intentionally left blank...
Page 50: ...49 FIGURE 10 2 LINE VOLTAGE FIELD CONNECTIONS FIGURE 10 3 LOW VOLTAGE PCB TERMINAL CONNECTIONS...
Page 52: ...51 FIGURE 10 4a 120V LWCO FIELD WIRING FIGURE 10 4b 24V LWCO FIELD WIRING...
Page 54: ...53 FIGURE 10 6 INTERNAL WIRING CONNECTIONS DIAGRAM...
Page 55: ...54...
Page 62: ...61 Lighting and Operating Instructions...
Page 82: ...81 FIGURE 14 6 CONTROLS LOCATION FIGURE 14 7 PRESSURE SWITCH TUBING CONNECTIONS...
Page 87: ...86 Blower Gas Valve Assembly for 150 180...
Page 90: ...89...
Page 103: ...102...