2.2 Checkout
Use this procedure to verify proper equipment operation.
2.2.1 Power-Up
Step 1.
Connect luminaire to a VARI*LITE Series 200 console via an
ACS Rack and repeater unit or via a cheater repeater.
Step 2.
Supply system power to luminaire and turn on console.
Step 3.
Watch for luminaire calibration. If luminaire does not calibrate
within 2 minutes, check lamp cable connection and address.
Step 4.
Verify that luminaire responds to control console commands.
(Instructions for exercising luminaire functions should be
referenced from the operator’s manual that accompanies that
particular controller or the Series 200 System Installation &
Checkout Manual .) If luminaire does not respond properly,
refer to Test and Fault Isolation sections in Chapter 3.