COMMISSIONING
48
5.3
Installation VCL2 / VCL3
5.3.1
Assembly preparation
NOTICE!
The following installation steps only show illustrations of the VCL2. Unless explicit ref-
erence is made in the individual descriptions, the descriptions always apply to the
VCL2 and VCL 3 system.
Tools and Measuring equipment
The following devices, tools and measuring equipment are necessary for assembly of
the conductor rails with accessories.
• Suitable means of transport for bringing the conductor rail to the installation site
(full-area support of the conductor rail).
• adjustable torque wrench for 1.4 Nm, 5 Nm, 7 Nm and 15 Nm
• ¼" reversible ratchet with an extension and nut with SW 7
• 200 mm steel rule
• Allen wrench, size 4
• soft face hammer head, about 50 mm dia.
• Screwdriver set
• mounting block
• Mounting handle for connector
• Cutting tool for making shorter lengths
• File for deburring the rail ends when making shorter sections
• Screw clamp for fixing the conductor system during the guide process
Preparation
• Protective measures have to taken against unauthorized access and operation
during the installation work
• The installation site must be clean and free of all objects
• There has to be adequate lighting over the entire installation site
• Tools for proper assembly of the system have to be available