2.22.3
Programming
The Control Station has been preset at the Väderstad factory depending on the type and size of the
machine it is supplied with. The Control Station settings need to be reentered after replacement or
a reset.
It is also possible to use the settings to adjust e.g., alarm delays, area metering, etc.
To enter the programming menu, keep
pressed while simultaneously switching on the pow-
er switch (1).
If the Control Station already has been switched on, switch to the programming menu by keeping
the button
depressed for 5 seconds. To complete programming and return to the drive
mode, select the last menu in the scroll list:
. Confirm with
.
Use the selection dial to select the desired menu. Selections are shown against a dark background.
Use
to confirm a selection and then select or change the value of the selected item. Confirm
the value/selection with
.
Menus:
1
Language. Select the desired language for alarm texts, etc.
2
Machine type. Select “RDA 600-800 S”.
3
Hydraulic feeding, Yes/No.
4
GPS, Yes/no. See ”
2.22.6 GPS (Global Positioning System)” on page 52
5
Number of pulses per revolution generated by the seed box drive sensor. Default setting:
360. (Only applies to hydraulic feed output)
6
Serial number. Record the serial number of the machine here. Select digits with the dial
and advance using
.
7
Machine width. Set the machine width here: 6.0 or 8.0 m.
8
Manual start. Select the intended drive speed here by keeping the button
de-
pressed. (Starting of feed output when drilling is commenced from a corner of the field, etc.;
only for hydraulic feed output.)
9
Output stop, Yes/No. Option Default setting: No.
10
Only if Yes has been selected in menu 9, Setting of lift time delay. Default setting 0.0
sec.
Summary of Contents for RAPID RDA S Series
Page 1: ...Ver 3 29 06 07 900236 dk Instruktioner S maskine RAPID serie RDA 600 800 S Nr 12 800 14 799...
Page 2: ...2 Ver 3 29 06 07...
Page 17: ...RDA 600 800 S Ver 3 29 06 07 17...
Page 20: ...Instructions and settings 20 Ver 3 29 06 07 2 8 Horizontal alignment Figure 2 18 A E C D B...
Page 71: ...RDA 600 800 S Ver 3 29 06 07 71 Figure 4 4...
Page 104: ...Appendices 104 Ver 3 29 06 07 6 3 2 Hydraulic diagram RDA 800 S Figure 6 2 444639...
Page 116: ...Appendices 116 Ver 3 29 06 07...
Page 117: ......