Commissioning (operation)
4.
4.
Fill the pump completely with new oil (more than mark "max.")
for corrosion protection.
Attention
Attention
: Before restarting the pump, drain oil to the maxi
‑
mum oil level (mark ”max.”).
5.
5. Close the manual gas ballast valve.
6.
6.
Clean the vacuum pump in the event of external contamina‑
tion.
7.
7.
Close the vacuum pump's inlet and outlet, e.g., with the
transport caps.
8.
8.
Package the vacuum pump such that it is protected from
dust; enclose desiccants if necessary.
9.
9.
Store the vacuum pump in a cool, dry location.
If damaged parts are stored for operational reasons, these should
be clearly identified as not ready for use
not ready for use
.
Carry out oil change and, if necessary, maintenance prior to use
if the pump has been stored for longer than one year.
IMPORTANT!
Summary of Contents for RE 2.5
Page 24: ...24 20901559_EN_RE_RZ_V7_230523 Introduction ...
Page 40: ...40 20901559_EN_RE_RZ_V7_230523 Installation and connection ...
Page 48: ...48 20901559_EN_RE_RZ_V7_230523 Installation and connection ...
Page 73: ...73 20901559_EN_RE_RZ_V7_230523 Appendix 8 8 8 8 CU Certificate CU Certificate CU Certificate ...
Page 76: ...76 20901559_EN_RE_RZ_V7_230523 ...
Page 77: ...77 20901559_EN_RE_RZ_V7_230523 ...
Page 78: ...78 20901559_EN_RE_RZ_V7_230523 ...