CONTROL MODULE 

REPLACEMENT KIT #550002965

INSTRUCTIONS 

CHB-100, CHB-130 and CCB-150

 P/N 240010533, Rev. A  [07/2014]

Kit installation shall be completed by qualified agency.

Figure 1 - Control Housing Screw 

 WARNING

Fire, explosion, asphyxiation and electrical shock hazard.  

Improper installation could result in death or serious injury.  

Read this instruction and understand all requirements, 

including requirements of authority having jurisdiction, 

before beginning installation.  Installation not complete until 

appliance operation verified per Installation, Operation & 

Maintenance Manual provided with boiler.

!

  

1. 

Follow instructions TO TURN OFF GAS TO APPLIANCE 

found in Installation, Operation & Maintenance Manual. 

Verify all electrical power to boiler is turned off.

 WARNING

Electrical shock hazard. Turn OFF electrical power supply at 

service panel.

!

  

2. 

Remove front jacket casing per instructions found in 

Installation, Operation & Maintenance Manual.

 WARNING

Burn hazard.  Verify heat exchanger has cooled or use 

appropriate personal protection equipment.

!

  

3. 

Remove control housing screw on lower right of control 

housing. See figure 1.

4. 

Slide control housing forward, it will fold down on its 

built in hinge. See figure 2

5. 

Remove two back cover screws.  Remove back cover.

See figure 2.

6. 

Disconnect all wiring connectors on control board. See 

figure 3.

7. 

Remove 2 screws holding board in place. Slide board 

out. See figure 3.

8. 

Replace board with new board, screw board in place. 

Connect wiring connectors on control board. See figure 3.

9. 

Replace back cover.

10. 

Fold control housing up and slide back into position. 

Secure with control housing screw. See figure 1.

Figure 2 - Control Housing Folded Down on Hinge

Control Housing 

Screw

Figure 3 - Screws Holding Board 

Back Cover 

Board Screws

Back Cover  

Screws