3.8 SYSTEM START UP
After having carried out the electrical connections, the control panel can be powered on and activated as follows:
•
Connect the batteries terminals.
•
Close the plastic cover of the control panel.
•
Power supply the control panel via the AC mains.
•
Wait a few minutes in order to let the conventional detectors perform the automatic calibration.
•
Perform the functional tests on the system and the points.
3.8.1 Functional tests
Circuits verification
•
Remove a point from the circuit and verify that the control panel signals the opening of the circuit by displaying a message,
turning the fault LED indicator ON and activating the buzzer.
If a malfunctioning is notified to the user, verify that:
•
There is no short circuit.
•
The polarity of the circuit and the points is correct.
•
The points are not consuming too much.
•