ÜKYP/YP Automatic Fuel Loading, Central System Heating Boiler Usage and Maintenance Manual
All electrical and water installations must be carried out by authorized installers, in accordance with
all applicable legal and technical rules and approved by the relevant legal institutions.
The fuels to be burned in the boiler should be kept at a distance of at least 800 mm from the boiler. It
is recommended to store fuels in a separate place.
Boilers should be installed on a concrete plinth 10 cm high from the floor in order to be protected from
water moisture and solid fuel ash dust. The concrete base prevents the fan from absorbing fuel or ash
dust on the ground.
Laying the assembly area with tiles and tile stones facilitates cleaning.
It is inconvenient to keep flammable, combustible and easily flammable materials in the
boiler room.
Installation site dimensions:
The boiler room should be in dimensions to provide the minimum dimensions given in the picture
below around the boiler. While the boiler is being placed, it is necessary to leave sufficient distance so
that fuel can be added to the bunker easily, the reducer and shaft under the bunker can be easily
removed, and the service can operate comfortably.
Dimension A: 60 cm more than the opening of the
boiler door;
Dimension B: It should be chosen considering the shaft
removal distance.
If the above measurements are followed, the
minimum given in the regulations
8 m
3
volume requirement is met.
There should be no faulty or doubtful electrical lines in the boiler room.
The 230 V electrical connection from the control panel must be connected to the mains
via a W automat.