Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53500160-01
Printed in U.S.A.
Form 50TC-8-16-01SI
CL-1
12-17
Replaces: 50TC-8-14-02SI
50TC-14SI
START-UP CHECKLIST
(Remove and use for job file)
MODEL NO.: ____________________________________________ SERIAL NO.: ____________________________
I. PRE-START-UP
VERIFY THAT ALL PACKAGING MATERIALS HAVE BEEN REMOVED FROM UNIT
VERIFY INSTALLATION OF OUTDOOR AIR HOOD
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTRUCTIONS
VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT
CHECK THAT INDOOR-AIR FILTERS ARE CLEAN AND IN PLACE
CHECK THAT OUTDOOR AIR INLET SCREENS ARE IN PLACE
VERIFY THAT UNIT IS LEVEL
CHECK FAN WHEELS AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND VERIFY
SETSCREW IS TIGHT
VERIFY THAT SCROLL COMPRESSORS ARE ROTATING IN THE CORRECT DIRECTION
VERIFY INSTALLATION OF THERMOSTAT
II. START-UP
ELECTRICAL
TEMPERATURES
PRESSURES
VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS
GENERAL
ECONOMIZER MINIMUM VENT AND CHANGEOVER SETTINGS TO JOB REQUIREMENTS (IF EQUIPPED)
VERIFY SMOKE DETECTOR UNIT SHUTDOWN BY UTILIZING MAGNET TEST
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Installation Instructions document.
SUPPLY VOLTAGE
L1-L2 ____________
L2-L3 _____________
L3-L1 ___________
COMPRESSOR AMPS 1
L1-L2 ____________
L2-L3 _____________
L3-L1 ___________
COMPRESSOR AMPS 2
L1-L2 ____________
L2-L3 _____________
L3-L1 ___________
SUPPLY FAN AMPS
L1-L2 ____________
L2-L3 _____________
L3-L1 ___________
OUTDOOR-AIR TEMPERATURE
_____________ °F DB (DRY BULB)
RETURN-AIR TEMPERATURE
_____________ °F DB _____________ °F WB (WET BULB)
COOLING SUPPLY AIR TEMPERATURE
_____________ °F
REFRIGERANT SUCTION
CIRCUIT A
_____________ PSIG
CIRCUIT B
_____________ PSIG
REFRIGERANT DISCHARGE
CIRCUIT A
_____________ PSIG
CIRCUIT B
_____________ PSIG
Summary of Contents for Carrier WeatherMaker 50TC A08 Series
Page 4: ...4 Fig 2 Unit Dimensional Drawing Size 08 09 12 Units...
Page 5: ...5 Fig 2 Unit Dimensional Drawing Size 08 09 12 Units cont...
Page 6: ...6 Fig 3 Unit Dimensional Drawing Size 14 Unit...
Page 7: ...7 Fig 3 Unit Dimensional Drawing Size 14 Unit cont...
Page 9: ...9 Fig 4 Unit Dimensional Drawing Size 16 Unit cont...
Page 13: ...13 Fig 8 Roof Curb Details Size 16 Unit...
Page 50: ...50 Fig 73 50TC 16 Control Box Component PremierLink Locations...
Page 51: ...51 Fig 74 Typical PremierLink Control Wiring Diagram...
Page 52: ...52 Fig 75 Typical PremierLink Control Wiring Diagram with Humidi MiZer System Option...
Page 64: ...64 Fig 106 Typical RTU Open Controller Wiring Diagram 50TC 08 14 Size Units...
Page 65: ...65 Fig 107 Typical RTU Open Controller Wiring Diagram 50TC 16 Size Unit...