2.2.2Hositing installation
1)
Adjust the steel wire rope to keep hanging beam level, to prevent the display tilt;
Fig 2-2
【
Fix Hanging Beam
】
2)
Install first horizon cabinets Mid to L-R side in turn;
Fig 2-3
【
Install Cabinets
】
Fig 2-4
【
Install Horizon Cabinets First
】