9
INSTALLATION: METHOD 2
SPARTAN
INSTALLATION: METHOD 2
SECURING WITH TOP HANGING BOLTS
1. Mark out the ceiling cut-out as per minimum hole dimensions below. Please refer to the size table on
pages 6. Cut out the hole for lift to fit through.
2. Route the Audio-Visual cables to the lift position in the ceiling. See the Cable Management instructions to
be followed post install.
3. A double power point is required in the ceiling to power the Spartan and the display panel.
NOTE: Access to the power point in the ceiling is advisable.
4. Raise the Spartan unit into the pre-cut hole from the underside into position.
5. Ensure the bottom of the unit is flush with the ceiling plaster.
6. Secure the unit in place using bolts and through the mounting holes.