1.
Position the Upper & Lower Support Arms as shown
in Figure 1 to the right.
2.
Slide the Arms together so that the alignment slots
are fully engaged.
3.
Set the assembled Arms onto the Base and align the
mounting holes.
4.
Insert 8 Carriage Bolts from the bottom of the base
upward through the bent feet.
5.
Install a Serrated-Flange Nut onto all 8 Bolts.
6.
Tighten all hardware securely.