34
Figure 12: Arrangement of wires on the power switch.
Brown wire to fuse
Blue wire to fuse
Brown wire to PL1 on power supply
Blue wire to PL1 on power supply
Slide a half-inch length of
3
/
16
" diameter heat shrink tubing onto both wires, and
solder them to the fuseholder, making sure of the correct wire orientation. Shrink on
the pieces of heat shrink tubing
Replace the insulation cover, and replace the fuse.
Close the case.
Perform the controller safety tests to confirm the ground resistance and leakage
current (see Sections 2.2.11 and 2.2.12).
Perform the complete controller functionality tests (see Section 2.2 or 2.3).
4.19 REPLACING THE POWER SWITCH
Pull off the four connectors, and push the
power switch
through from the inside of
the case by using a screwdriver to collapse the retaining clips.
Push in the new switch from the outside of the case and re-fit the four connectors
with the wires connected as previously (see Figure 12).
Close the case.
Perform the controller safety tests to confirm the ground resistance and leakage
current (see Sections 2.2.11 and 2.2.12).
Perform the complete controller functionality tests (see Section 2.2 or 2.3).