Installation and mounting
7.10.3 Mounting variant 3
With this mounting variant, you first glue the base frame onto the foundation
or the finished floor. Then mount the pedestrian gate on the base frame.
Required material, included in the scope of delivery:
›
Screw
5/16" x 7/8" long
stainless steel
›
Screw
5/16" x 5/8" long
, stainless steel
›
Washer
3/8"
dia.
, stainless steel
Required material (not included in the scope of delivery):
›
Base frame FURA100
›
Adhesive set BSSKL100 for gluing the base frame
Requirements
›
The foundation / finished floor has been built.
›
The empty conduits were laid.
›
The foundation / finished floor has hardened.
IMPORTANT!
Follow the separate instructions as well as the packaging labels
for the surface cleaner, construction adhesive and remover.
The floor must be free of paint and varnish.
Foundation and empty conduit plan:
Page 39, Fig. 11 and
Base frame FURA100:
1. Base frame and aligning.
NOTICE
Incorrect alignment of the pedestrian gate! The pedestrian gate is not
symmetrically constructed. Align the pedestrian gate so that the passage
side is on the correct side. Observe foundation plan.