Traverse Installation and Commissioning Guide, Section 10: Power Installation and Cabling Procedures
Connect Supply Cables to the Central Office Source
Page 10-28
Turin Networks
Release TR3.2.1
Table 10-9 Connect Supply Cables to the Central Office Source
Step
Procedure
1
WARNING!
Before connecting the supply cables, go to the front of the
PDAP and verify that all circuit breakers are in the OFF position,
TPA fuse holders are empty, and that GMT fuse positions are empty
or contain dummy fuses.
Figure 10-17 PDAP-4S Front View
Figure 10-18 PDAP-15A Front View
Figure 10-19 PDAP-2S Front View
Make sure TPA fuse holders are empty
Make sure GMT fuses are empty or contain dummy fuses
Make sure GMT fuses are empty or contain dummy fuses
A1
A2
B1
B2
Circuit Breakers—OFF
Circuit Breakers—OFF
Make sure GMT fuses are empty or contain dummy fuses