Traverse Installation and Commissioning Guide, Section 10: Power Installation and Cabling Procedures
Connect PDAP-4S Battery Return Distribution Cables
Page 10-12
Turin Networks
Release TR3.2.1
Connect
PDAP-4S
Battery Return
Distribution
Cables
The PDAP-4S distributes central office battery return (RETURN) to up to four
Traverse 1600 or Traverse 2000 shelves in a rack. Follow these steps to connect battery
return distribution (RETURN) cables from a Traverse shelf to the PDAP-4S.
Note:
Traverse 2000 main backplane graphics are used in the following procedure.
Battery return distribution (RETURN_A, common RETURN_A RETURN_B, and
RETURN_B) terminals are located in the same place on the Traverse 1600 backplane.
Table 10-4 Connect PDAP-4S Battery Return Distribution Cables
Step
Procedure
1
Did you first complete the
Connect PDAP-4S Battery Distribution
•
Yes.
Continue to the next step.
•
No.
Go to Table 10-3 Connect PDAP-4S Battery Distribution Cables,
page 10-9 to complete this cabling first.
2
Use the supplied RETURN cable or use a crimping tool to attach a
double-hole copper barrel cable lug to one end of the battery return
distribution (RETURN) wire for the battery return distribution cable
connection to the Traverse shelf.
3
Remove SEMS screws from the Traverse shelf RETURN_A power
terminals using a 1/4-inch socket (or nutdriver).
4
Place the battery return distribution double-hole copper barrel cable lug
over the RETURN_A power terminals. Replace and tighten the SEMS
screws using a 1/4-inch socket (or nutdriver).