Chapter 2 Traverse System Hardware Installation
Install the Front Inlet Fan Tray Holder
Release TR3.2.1
Turin Networks
Page 7-11
Install the
Front Inlet Fan
Tray Holder
The front inlet fan tray holder (with integrated air ramp) is required to cool the Traverse
shelf during normal operation. Follow these installation steps.
Note:
Standard conductive plated rack adapters may be required for installation. If so,
refer to
Important:
Install the front inlet fan tray holder directly below the
Traverse shelf so that no gap remains in order to ensure proper air flow.
Table 7-5 Install the Front Inlet Fan Tray Holder
Step
Procedure
1
It is easier to connect the front inlet fan tray holder power cable to the
Traverse backplane before installing the front inlet fan tray holder in the
rack. Grasp the power cable and bring it out the top of the front inlet fan
tray holder.
2
Bring the fan tray holder power cable with the 18-pin connector up to its
mating connector on the Traverse main backplane. Push up on the
connector until it locks into position. The tab on the connector locks it into
place.
Figure 7-4 Front Inlet Fan Tray Connection at the Main Backplane
3
Lift and position the fan tray holder directly below the Traverse shelf so
that there is no gap between the shelf and the fan tray holder.
Note:
The front inlet fan tray holder flange has two 1-RU slots.
4
Align the flange holes with the holes on the rack.
5
Place thread-forming screws through the flange slot on each side of the
front inlet fan tray holder and into the rack.
1
6
1
5
1
4
1
3
1
2
1
1
1
0
9
8
7
6
5
4
3
2
1
Main Backplane
Fan Tray Holder
Connector
Front Inlet Fan
Tray Power
Cable
Front Inlet Fan Tray
Holder Internal
Connector