Zanté electric shower
COMMISSIONING
The first operation of the shower should flush
out any remaining unit debris and guarantee
that the heater unit contains water before the
elements are switched on. This must be done
with the flexible hose screwed to the outlet
without the showerhead attached. The outlet of
the hose should be directed to waste.
Note:
Check that the ‘START/STOP’ button is
not depressed in the cover, otherwise water will
flow as soon as the electricity is switched on.
Before turning on the electric and mains water
supplies to the shower, check that the power
selector is at the ‘COLD’ position
(fig.9)
and
the temperature control is rotated fully clockwise
to ‘MAX’, (minimum flow position
(fig.0)
.
Note:
Failure to turn the control to ‘max’ may
cause the PRD to operate.
Turn on the mains water supply to the shower
at the isolating stop valve and then turn on the
electric supply to the shower at the isolating
switch. The power indicator will light.
Press the ‘START/STOP’ button
(fig.)
and
wait until water starts to flow from the flexible
hose.
Slowly rotate the temperature control fully
anti-clockwise to ‘MIN.’, (the maximum flow
position)
(fig.)
.
It will take approximately thirty seconds for a
smooth flow of water to be obtained when air
and debris is being dispersed from the shower.
When a smooth flow of water is obtained, rotate
the temperature control from ‘min’ to ‘max’
several times to release any trapped air within
the unit.
Once flushing out has been completed, stop the
water flow by pressing the ‘START/STOP’ button.
The shower is now ready for normal operation.
Fig.9
Fig.0
Fig.
Fig.
WARNING!
before normal operation of the
shower, it is essential the following
commissioning procedure is
completed correctly.