51
Transport and installation
TNL20
DTE022DE - 24.06.2021
Installation of the machine
Electrical connection
Check the connected load according to the data and conditions in Chapter
“Electrical connection“
.
Aligning and anchoring the machine
• Screw the adjusting screw
D
(bearing points
A-D
see layout and installation
plan) upward until it lifts completely off of the footplate.
• Loosen and remove the cover
(4)
.
4
• Place a spirit level on the surface
(5)
provided on the main spindle.
5
• Align the machine to the height position of 1150 mm
of main spindle
height
by turning the adjusting screws
A, B
, and
C
.
The machine must be adjusted exactly to
1150 mm main spin-
dle height
so that the chip conveyor can be inserted. The maxi-
mum permissible deviation is 0.5 mm per 1000 mm
Summary of Contents for TNL20
Page 6: ...Table of Contents 6 Transport and installation TNL20 DTE022EN 02 08 2022...
Page 10: ...10 Transport and installation TNL20 DTE022EN 14 03 2022 Safety...
Page 20: ...20 Transport and installation TNL20 DTE022EN 14 03 2022 General...
Page 66: ...66 Transport and installation TNL20 DTE022EN 14 03 2022 Electrical connection...
Page 68: ...68 Transport and installation TNL20 DTE022DE 24 06 2021 Operating material...
Page 70: ...70 Transport and installation TNL20 DTE022DE 24 06 2021 Pneumatic connection...
Page 72: ...72 Transport and installation TNL20 DTE022DE 24 06 2021 Switching on the machine...
Page 73: ......