6
Installation
EVP Chiller Considerations
The EVP chiller must be installed indoors unless:
Outdoor temperatures are always above 32 F.
System circulating liquid is a non-freezing glycol-
type solution selected for prevailing ambient
temperatures.
Chiller is protected from freeze-up by properly
installed and applied insulation and heat tape.
Note: To prevent internal chiller damage due to
freezing, do not install the EVPB chiller outdoors
without adequate freeze protection.
Allow adequate clearance at one end of the chiller to pull
the evaporator tubes and for; water and refrigerant piping
connections, space to perform service procedures, i.e. read
gauges, thermometers, and operate water system valves.
Unit Dimensions & Weight Information
Overall unit dimensional data for each unit is illustrated in
Figure 3-2A.
A Center-of-Gravity illustration and the dimensional data for
the unit is shown in Figure 3-3.
Table 3-1A lists the typical operating and point loading
weights for the unit.
EVP chiller barrel mounting footprints and overall dimen-
sional data is illustrated in Figure 3-2B.
Table 3-1B lists the typical EVP operating weights and gen-
eral data.
Foundation
If the unit is installed at ground level, elevate it above the
snow line. Provide concrete footings at each support loca-
tion or a slab foundation for support. Refer to Table 3-1A for
the unit operating and point loading weights when con-
structing the footing foundation.
Anchor the unit to the footings or slab using hold down bolts
or isolators. Isolators should be installed to minimize the
transmission of vibrations into the building. Refer to the
“Unit Isolation” section for spring or rubber isolator installa-
tion instructions.
For rooftop applications, ensure the roof is strong enough to
support the unit. Refer to Table 3-1A for the unit operating
weights.
Anchor the unit to the roof with hold-down bolts or isolators.
Follow the instructions under “Unit Isolation” for proper iso-
lator placement and installation.
Check with a roofing contractor for proper waterproofing
procedures.
The EVP chiller barrel must be installed level and should be
mounted on a base that will adequately support the operat-
ing weight. Refer to Table 3-1B for operating weights.
Unit Inspection
As soon as the unit arrives at the job site
[ ] Verify that the nameplate data matches the data on the
sales order and bill of lading (including electrical data).
[ ] Verify that the power supply complies with the unit name-
plate specifications.
[ ] Visually inspect the exterior of the unit, including the roof,
for signs of shipping damage.
[ ] Check for material shortages. Refer to the Component
Layout and Shipwith Location illustration.
If the job site inspection of the unit reveals damage or mate-
rial shortages, file a claim with the carrier immediately.
Specify the type and extent of the damage on the "bill of
lading" before signing.
[ ] Visually inspect the internal components for shipping
damage as soon as possible after delivery and before it
is stored. Do not walk on the sheet metal base pans.
N O S T E P S U R F A C E !
FOR ACCESS TO COMPONENTS, THE BASE SHEET
METAL SURFACE MUST BE REINFORCED.
Bridging between the unit's main supports may con-
sist of multiple 2 by 12 boards or sheet metal grating.
Failure to comply can cause severe personal injury
or death from falling.
[ ] If concealed damage is discovered, notify the carrier's
terminal of damage immediately by phone and by mail.
Concealed damage must be reported within 15 days.
Request an immediate joint inspection of the damage by
the carrier and the consignee. Do not remove damaged
material from the receiving location. Take photos of the
damage, if possible. The owner must provide reasonable
evidence that the damage did not occur after delivery.
[ ] Notify the appropriate Trane office before installing or re-
pairing a damaged unit.
Unit Clearances
Figure 3-1 illustrates the minimum operating and service
clearances for either a single, multiple, or pit application.
These clearances are the minimum distances necessary to
assure adequate serviceability, cataloged unit capacity, and
peak operating efficiency.
Providing less than the recommended clearances may re-
sult in condenser coil starvation or recirculation of hot con-
denser air.
Locate the unit as close to the applicable system support
equipment as possible to minimize refrigerant piping
lengths.
Summary of Contents for RAUC-IOM-15
Page 8: ...8 Figure 3 2A RAUC C80 Unit Dimensional Data Recommended Clearances...
Page 9: ...9 Figure 3 2A Continued RAUC D10 Unit Dimensional Data Recommended Clearances...
Page 10: ...10 Figure 3 2A Continued RAUC D12 Unit Dimensional Data Recommended Clearances...
Page 11: ...11 Figure 3 2B EVPB C80 Evaporator Chiller Dimensions...
Page 12: ...12 Figure 3 2B Continued EVPB D10 Evaporator Chiller Dimensions...
Page 13: ...13 Figure 3 2B Continued EVPB D12 Evaporator Chiller Dimensions...
Page 14: ...14 Figure 3 2B Continued EVPB C80 through D12 Chill Water Pipe Stubout Dimensions...
Page 35: ...35 Installation Continued Field Connection Diagram Notes for all System Control Options...
Page 57: ...57 Figure 5 5 Typical Scroll Compressor Terminal Block System Start Up Continued...
Page 67: ...67...
Page 68: ...68...