RT-SVX36G-EN
165
Startup Checklists
Verify all fans rotate in proper direction
Verify fan amperages within nameplate specs (Please document on log sheet)
Unit Configuration and Setup
Verify model number in the UCM configuration matches unit model number on name plate
Configure unit using IOM and critical control parameters listed in
Air Cooled Condenser (Digit 27)
All coil fins inspected and straightened
Condenser fans are rotating freely
Verify the fan blade set-screws to the motor shaft of the condenser fan assemblies are tight
Electric Heat (If Applicable)
Electric heat circuits have continuity
Perform electric heat start-up procedure outlined in IOM
Gas Heat (If Applicable)
Gas heat piping includes drip leg previously installed by controlling contractor
Gas heat flue assembly fully installed
Gas heat condensate line + heat tape installed where applicable
Verify heating system matches name plate
Optional Gas Burner (Digit 9)
2 Stage Gas Burner Set-up procedure in IOM
Modulating Burner Set-up procedure in IOM
Hot Water Heat (If Applicable)
Verify hot water pipes are proper size, routed through the base and no leaks are present
Verify swing joints or flexible connectors are installed next to hot water coil
Verify gate valve is installed in the supply and return branch line
Verify three way modulating valve is installed with valve seating against the flow
Verify coil venting is installed if water velocity is less than 1.5 feet per second
Steam Water Heat (If Applicable)
Verify steam pipes are proper size, routed through the base and no leaks are present
Verify steam heat swing check vacuum breakers installed and vented
Verify 2-way modulating valve has been installed
Verify steam trap installed properly with discharge 12" below the outlet connection on the coil
System Checkout
Verify system airflow
Verify dampers open and close properly
Adjust fresh air damper travel
Verify compressor operation, voltage and amperage matches name plate information (Please document on log sheet)
Verify superheat and subcooling normal (Please document on log sheet)
Operating log completed
All panels/doors secured
Complete all required documentation
Table 53. Startup checklist (continued)— 20-75 ton air-cooled
Verify Task
Completed