background image

Page 18 

                 

Installer’s Guide

Table 3. Gas Flow in Cubic Feet Per Hour 

2 Cubic Foot Dial

Sec.

Flow

Sec.

Flow

Sec.

Flow

Sec.

Flow

  8

 900

  29

 248

  50

 144

  82

  88

  9

 800

  30

 240

  51

 141

  84

  86

 10

 720

  31

 232

  52

 138

  86

  84

 11

 655

  32

 225

  53

 136

  88

  82

 12

 600

  33

 218

  54

 133

  90

  80

 13

 555

  34

 212

  55

 131

  92

  78

 14

 514

  35

 206

  56

 129

  94

  76

 15

 480

  36

 200

  57

 126

  96

  75

 16

 450

  37

 195

  58

 124

  98

  73

 17

 424

  38

 189

  59

 122

 100

  72

 18

 400

  39

 185

  60

 120

 104

  69

 19

 379

  40

 180

  62

 116

 108

  67

 20

 360

  41

 176

  64

 112

 112

  64

 21

 343

  42

 172

  66

 109

 116

  62

 22

 327

  43

 167

  68

 106

 120

  60

 23

 313

  44

 164

  70

 103

 124

  58

 24

 300

  45

 160

  72

 100

 128

  56

 25

 288

  46

 157

  74

  97

 132

  54

 26

 277

  47

 153

  76

  95

 136

  53

 27

 267

  48

 150

  78

  92

 140

  51

 28

 257

  49

 147

  80

  90

 144

  50

Figure 18. Burner and Valve

Outlet Pressure Boss

2nd Stage (HI) 
Manifold Pressure 
Adjustment

Regulator 
Vent

Inlet Pres-
sure Boss

Gas Valve 
ON/OFF 
Toggle 
Switch

High Fire Coil 
Terminal (H)

1st Stage 
(LO) 
Manifold 
Pressure 
Adjustment

Common 
Terminal (C)

Coaxial Coil 
Terminal (M)

Chart Flow Reading

2

Chart Flow Reading

4

10X Chart Flow Reading

4

For 1 Cu. Ft. Dial Gas Flow CFH = 

For 1/2 Cu Ft. Dial Gas Flow CFH = 

For 5 Cu. Ft. Dial Gas Flow CFH = 

  4. Before connecting the piping circuit to the unit, bleed the air 

from the supply line and then cap or plug the line and test the 
pressure at the tapped shut-off cock.  The pressure reading 
should not exceed 14 inches water column.

  5.  Using an appropriate backup wrench on the gas valve inlet boss, 

connect the gas piping to the unit.  Check the completed piping 
for leaks using a soap and water solution or the equivalent.

  6. After installation of the gas pipe in the unit, the pipe opening 

should be closed with the filler/barrier plug provided.

Manifold Pressure

Check the manifold pressure at the unit gas valve.  Do not exceed 
the recommended pressure shown on the unit nameplate.

Input Check and Adjustment

1. Make sure all gas appliances are off except the furnace.
2. Clock the gas meter with the furnace operating (determine the 

dial rating of the meter) for one revolution.

3. Match the “Sec” column in the gas flow (in cfh) Table 3, with the 

time clocked.

4. Read the “Flow” column opposite the number of seconds 

clocked.

5. Use the following factors if necessary.

NOTE: 

 For manifold pressures and orifice sizes for gas with other 

BTU ratings, contact the local gas utility. Manifold  

 

pressure should be 1.8  (low) to 3.5 (high) inches water column  
(+0.1).  Input for natural gas must not exceed the value shown on 
the unit nameplate.

 

6. Multiply the final figure by the heating value of the gas obtained 

from the utility company and compare to the nameplate rating.  
This must not exceed the nameplate rating.

7. Changes can be made by adjusting the manifold pressure.

a. Attach a manifold pressure gauge.
b. Remove the slot screw on top of the gas valve for 1st stage 

manifold pressure adjustment.  Remove slot screw on outlet 
side for 2nd stage adjustment (See Figure 18).

c. Turn the adjustment nut in to increase the gas flow rate, and 

out to decrease the gas flow rate using a 3/32" hex wrench.

Summary of Contents for 4YCZ6024

Page 1: ...ures on the fan Operating the unit without the access panels properly installed may result in severe personal injury or death WARNING SAFETY HAZARD This information is for use by individuals having adequate backgrounds of electrical and mechanical experience Any attempttorepairacentralairconditioningproductmayresult inpersonalinjuryand orpropertydamage Themanufacturer or seller cannot be responsib...

Page 2: ...R 410A operating pressure exceeds the limit of R 22 Proper service equipment is required Failure to use proper service tools may result in equipment damage or personal injury SERVICE Use only R 410A Refrigerant and approved POE compres sor oil IMPORTANT Wear appropriate gloves arm sleeve protectors and eye protection when servicing or maintaining this equipment PRECAUTIONARY MEASURES Avoid breathi...

Page 3: ...g 16 Gas Piping Installation 16 Pipe Delivery Schedule natural gas only 17 Gas Pressure Set up Precautions 17 Gas Supply Line Pressure all fuels 17 Verify Manifold Pressure 18 Input Check and Adjustment 18 High Altitude Installation 19 Air Filter Installation 19 Electrical Wiring 19 Electrical Connections 18 Electrical Power 19 Disconnect Switch 19 Over current Protection 19 Power Wiring 19 Contro...

Page 4: ... Determine Unit Clearances Figure 1 4YCZ6024 6036 1 of 3 Figures 1 through 6 show the unit critical dimensions DWG NO D673947G01_REVC NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit ...

Page 5: ...Page 5 Installer s Guide Figure 2 4YCZ6024 6036 2 of 3 ...

Page 6: ...uide Step 2 Determine Unit Clearances Figure 1 4YCZ6024 6036 3 of 3 Figures 1 through 6 show the unit critical dimensions NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit ...

Page 7: ...Page 7 Installer s Guide Figure 4 4YCZ6048 through 4YCZ6060 1 of 3 NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit ...

Page 8: ...Page 8 Installer s Guide Figure 5 4YCZ6048 through 4YCZ6060 2 of 3 ...

Page 9: ...Page 9 Installer s Guide Figure 6 4YCZ6048 through 4YCZ6060 3 of 3 ...

Page 10: ...r to the Installation section for instruction on converting the supply and return airflow covers to down airflow 3 The field assembled Roof Mounting Curb BAYCURB050A or BAYCURB051A or a field fabricated curb should be in place before the unit is hoisted to the roof top The Roof Mounting Curb frame must be installed on a flat level section of the roof maximum of 1 4 per foot pitch and provide a lev...

Page 11: ...clearance to combustible mate rial shall be maintained on air outlet duct Rooftop Installation Curb Mounting Convert Horizontal Airflow to Down Airflow The factory ships the unit for horizontal airflow Perform this procedure to convert the unit to down airflow 1 Remove the three 3 sheet metal screws securing the supply aircover and the four 4 sheet metal screws securing the return air cover from t...

Page 12: ...tabs or flanges Failure to observe these warnings may result in equipment damage 1 Before preparing the unit for lifting check the unit dimension drawings for center of gravity for lifting safety Figures 1 to 6 page 4 9 Because of placement of internal components the unit s weight may be unevenly distributed Approximate unit weights are also provided in the unit drawings NOTE When unit rigging and...

Page 13: ... roof top applications using field fabricated ducts and sleeper rails rather than a curb or frame use the following procedure 1 Locate and secure the sleeper rails to the roof Three 3 sleeper rails are required One on each end to support the edges of the unit and one across the center of the unit The center rail must run inside both drip lips Vibration isolators should be installed as indicated on...

Page 14: ...sible for the unauthorized use of this drawing and expressly disclaims any liability for damages resulting from such unauthorized use Gasket Seal Spreader Bars Base of unit rest on top of curb rails Drip lip on perimeter of unit Top shipping skid attached to unit IMPORTANT To prevent damage to the sides and top of the unit when hoisting retain the top shipping skid on the unit or use spreader bars...

Page 15: ...orizontal Airflow Application with Frame Supply Air Return Air Roof Flashing Channel Iron Center Support Center Sup port required on all Frame Applications Angle Iron Frame Roof Flashing Return Air Angle Iron Frame Roof Flashing Supply Air Channel Iron Center Support Center Support required on all Frame Applications ...

Page 16: ...oise and vibration transmission Elbows with turning vanes or splitters are recommended to minimize air noise and resistance The first elbow in the ductwork leaving the unit should be no closer than two 2 feet from the unit to minimize noise and resistance To prevent leaking do not attach the ductwork to the bottom of the unit base refer to the bottom example in Figure 14 A 3 4 inch female NPT cond...

Page 17: ...e making the gas pipe connection give serious consideration to providing the clearance necessary to remove the accesspanelsontheunit e g economizerandfilteraccesspanels NOTE In the absence of local codes the installation must con form with American National Standard Z223 1 National Fuel Gas Code Latest Revision The available gas supply must agree with the required gas supply marked on the unit nam...

Page 18: ...nchonthegasvalveinletboss connect the gas piping to the unit Check the completed piping for leaks using a soap and water solution or the equivalent 6 After installation of the gas pipe in the unit the pipe opening should be closed with the filler barrier plug provided Manifold Pressure Check the manifold pressure at the unit gas valve Do not exceed the recommended pressure shown on the unit namepl...

Page 19: ...hat require 49 orifices for altitudes from 7000 8000 orifices must be changed to 50 HIGH ALTITUDE DERATE CHART NAT Altitude In Feet Inputs shown are with factory orifices 3 5 WC High Fire 1 8 WC Low Fire Natural Gas heating value of 950 btu cuft Electrical Power It is important that proper electrical power be available for the unit Voltage variation should remain within the limits found on the uni...

Page 20: ...itioning systems been checked at the service ports for charge and leak tested if necessary Does the condenser fan and indoor blower turn free without rub bing and are they tight on the shafts Has the indoor blower speed been determined and the proper speed been set See the Unit Wiring Diagram Has all work been done in accordance with applicable local and national codes Are all covers and access pa...

Page 21: ...Page 21 Installer s Guide Figure 22 4YCZ6 Field Wiring Diagram NOTE For economizer wiring instructions see the Installer s Guide that came with your economizer ...

Page 22: ...cooling setpoint to above room temperature Heating Cycle Theseunitsareequippedwithasolid stateignitioncontrolthatlights the burners each time the thermostat calls for heat The burners are extinguished during the OFF cycle The gas heating section of the unit can be started using the follow ing procedure 1 Be sure the thermostat is at its lowest setting and the power to the unit is off a Turn the ma...

Page 23: ...ond postpurge The indoor blower motor will continue to operate at the current speed for 60 or 90 seconds after the flames are extinguished Sequence of Operation Safety Sequences This product is equipped with safety devices to protect against abnormal conditions The temperature limit switch TCO is located on the blower barrier andcanbeaccessedthroughtheblowercompartment Thisautomatic reset device p...

Page 24: ... damage Do not store combustible materials gasoline or other flammable vapors or liquids near the unit WARNING Someoftheperiodicmaintenancefunctionsofthe4YCZ6unitcan beperformedbytheowner thisincludesreplacingthedisposable or cleaning the permanent air filters cleaning the unit cabinet and conducting a general unit inspection on a regular basis Filters When the system is in constant operation insp...

Page 25: ... Hood and Combustion Blower Cleaning Manifold Pressure Check and Adjust 1 Connect a manometer to the pressure tap at the outlet side of the unit s gas valve remove the Control Heat access panel Read the manifold pressure with the burners firing See Figure 16 on page 17 for gas valve connections 2 If the manifold pressure reading does not match the value indicated on the unit s nameplate the unit s...

Page 26: ... 3 Flashes Pressure switch problem detected Fast Flash Rate Not used 4 Flashes High Limit switch protection device open Steady ON Normal No Call for Heat 5 Flashes Flame sensed and gas valve not energized or flame sensed and no W signal 6 Flashes Flame Rollout Switch open 7 Flashes Thermostat miswired W1 W2 Fast Flash Rate The LED will flash on for 1 4 second and off for 1 4 second Slow Flash Rate...

Page 27: ...Page 27 Installer s Guide ...

Page 28: ...uide Trane 6200 Troup Highway Tyler TX 75707 9010 The manufacturer has a policy of continuous product and product data improvement and it reserves the right to change design and specification without notice 2017 Trane 09 18 ...

Reviews: