background image

 

Page 13

Installer’s Guide

Rooftop Installation -- Frame Mounting

For roof top applications using field fabricated frame and ducts, use 

the following procedure:

  1. Locate and secure the frame to the roof by bolting or welding.  

Frame must provide adequate center support via a cross mem-

ber centrally located channel rail. See Figures 12 and 13 on 

page 15. Vibration isolators should be installed as indicated in 

Figure 9, adjust as necessary for your frame. The isolators must 

be placed on base pan, not drip lip. Add flashing as required. 

Flashing must conform to local building codes.

  2. Prepare the hole in the roof in advance of installing the unit.

  3. Secure the horizontal or down airflow ducts to the roof. Refer 

to the previous Convert from Horizontal Airflow to Down Airflow 

section on page 11,  if conversion is needed. 

  4. All fabricated outdoor ducts should be as short as possible.
  5. Place the unit on the frame.  Refer to Figures 12 or 13 on page 

15.

  6. The unit must be mounted level for proper drainage of water 

through the holes in the base pan.

  7. Secure the unit to the frame.
  8. Insulate any ductwork outside of the structure with at least two 

(2) inches of insulation and then weatherproof.  There must be 

a weatherproof seal where the duct enters the structure.

  9. The unit should not be exposed to direct roof water runoff.
 10. Flexible duct connectors must be of a flame retardant material.  

All duct work outside of the structure must be insulated and 

weatherproofed in accordance with local codes.

 11. Access and service clearances for the unit must be given care-

ful consideration when locating the duct entrance openings.  

Figures 1 to 6, on pages 4-9, provide unit dimensions.

12.  Continue with the following installation sections to complete 

the installation: Ductwork on page 16, Gas Piping on page 17, 

Filter on page 19, 

and Electrical Wiring on page 19.

Figure 9.  Vibration Isolators/Snow Feet Locations

Small Cabinet 

*****018-036

Medium Cabinet 

*****042-060

Rooftop Installation -- Flat Roof - No Curb/Frame

For roof top applications using field fabricated ducts and sleeper 

rails rather than a curb or frame, use the following procedure:

  1.  Locate and secure the sleeper rails to the roof.  Three (3) sleeper 

rails are required. One on each end to support the edges of the 

unit and one across the center of the unit. The center rail must 

run inside both drip lips. Vibration isolators should be installed 

as indicated on Figure 9, adjust as necessary for your sleeper 

rails. The isolators must be placed on base pan, not drip lip. Add 

flashing as required. Flashing must conform to local building 

codes.

  2. Prepare the hole in the roof in advance of installing the unit.

  3. Secure the horizontal or down airflow ducts to the roof. Refer 

to the previous Convert from Horizontal Airflow to Down Airflow 

section on page 11,  if conversion is needed. 

  4. All fabricated outdoor ducts should be as short as possible.
  5. Place the unit on the rails.  
  6. The unit must be mounted level for proper drainage of water 

through the holes in the base pan.

  7. Secure the unit to the rails.
  8. Insulate any ductwork outside of the structure with at least two 

(2) inches of insulation and then weatherproof.  There must be 

a weatherproof seal where the duct enters the structure.

  9. The unit should not be exposed to direct roof water runoff.
 10. Flexible duct connectors must be of a flame retardant material.  

All duct work outside of the structure must be insulated and 

weatherproofed in accordance with local codes.

 11. Access and service clearances for the unit must be given care-

ful consideration when locating the duct entrance openings.  

Figures 1 to 6, on pages 4-9, provide unit dimensions.

12.  Continue with the following installation sections to complete 

the installation: Ductwork on page 16, Gas Piping on page 17, 

Filter on page 19, 

and Electrical Wiring on page 19.

IMPORTANT: 

 Unit requires vibration isolator supports in the general areas shown. Locate 3/4" thick vibration isolators on 

the bottom of the basepan as illustrated by black dots for ground level pad applications. Modify vibration isolator location 

as necessary for frame and rail applications. 

NOTE: 

 These views represent the base as viewed looking up from underneath the unit.

Summary of Contents for 4YCY4024

Page 1: ...inherent hazards during installation and service the electrical supply must be disconnected and the main gas valve must be turned off If operating checks must be performed with the unit operating it i...

Page 2: ...ENING SYSTEM Failure to follow proper procedures can result in personal illness or injury or severe equipment damage RECONNECT ALL GROUNDING DEVICES All parts of this product that are capable of condu...

Page 3: ...erwriters Laboratory An LP Gas conver sion kit is available Extreme mounting kits for slab and curbs are also available Packaged units are designed for outdoor mounting with a vertical condenser disch...

Page 4: ...ep 2 Determine Unit Clearances Figure 1 4YCY4024 through 4YCY4036 1 of 3 Figures 1 through 6 show the unit critical dimensions NOTE The view labeled Bottom Side represents the Base as viewed looking u...

Page 5: ...Page 5 Installer s Guide Figure 2 4YCY4024 through 4YCY4036 2 of 3...

Page 6: ...Page 6 Installer s Guide Figure 3 4YCY4024 through 4YCY4036 3 of 3...

Page 7: ...Page 7 Installer s Guide Figure 4 4YCY4042 through 4YCY4060 1 of 3 NOTE The view labeled Bottom Side represents the Base as viewed looking up from underneath the unit...

Page 8: ...Page 8 Installer s Guide Figure 5 4YCY4042 through 4YCY4060 2 of 3...

Page 9: ...Page 9 Installer s Guide Figure 6 4YCY4042 through 4YCY4060 3 of 3...

Page 10: ...Refer to the Installation section for instruction on converting the supply and return airflow covers to down airflow 3 The field assembled Roof Mounting Curb BAYCURB050A or BAYCURB051A or a field fabr...

Page 11: ...ce to combustible mate rial shall be maintained on air outlet duct 4 Attach the supply and return air ducts to the unit as explained Rooftop Installation Curb Mounting Convert Horizontal Airflow to Do...

Page 12: ...he unit casing casing hardware corner lugs angles tabs or flanges Failure to observe these warnings may result in equipment damage 1 Before preparing the unit for lifting check the unit dimension draw...

Page 13: ...For roof top applications using field fabricated ducts and sleeper rails rather than a curb or frame use the following procedure 1 Locateandsecurethesleeperrailstotheroof Three 3 sleeper rails are re...

Page 14: ...drawing The manufacturer is not responsible for the unauthorized use of this drawing and expressly disclaims any liability for damages resulting from such unauthorized use Gasket Seal Spreader Bars B...

Page 15: ...rizontal Airflow Application with Frame Supply Air Return Air Roof Flashing Channel Iron Center Support Center Sup port required on all Frame Applications Angle Iron Frame Roof Flashing Return Air Ang...

Page 16: ...wo 2 feet from the unit to minimize noise and resistance To prevent leaking do not attach the ductwork to the bottom of the unit base refer to the bottom example in Figure 14 Condensate Drain Piping A...

Page 17: ...SURE DROP OF 0 3 INCH W C AND 0 6 SP GR GAS IMPORTANT Before making the gas pipe connection give serious consideration to providing the clearance necessary to remove the accesspanelsontheunit e g econ...

Page 18: ...cap or plug the line and test the pressure at the tapped shut off cock The pressure reading should not exceed 14 inches water column 5 Usinganappropriatebackupwrenchonthegasvalveinletboss connect the...

Page 19: ...in the absence of local codes with the National Electrical Code ANSI NFPA 70 Latest Revision NOTE This unit is factory wired for 230V See wiring dia gram for 208V conversion NOTE For branch circuit w...

Page 20: ...Switch Provide an approved weatherproof disconnect within close proxim ity to and within sight of the unit If disconnect must be mounted to the cabinet the location shown in Figure 21 should be the o...

Page 21: ...757192i2 B G Y W1 W2 R COMMON FAN COMPRESSOR HEAT FIRST STAGE HEAT SECOND STAGE 24V UNIT CONTROL BOX GROUND WIRE 3 PH POWER UNIT NOTE 1 1 PH POWER B G Y W1 W2 R COMMON FAN COMPRESSOR HEAT FIRST STAGE...

Page 22: ...Are all covers and access panels in place to prevent air loss and safety hazards NOTE Do not use the PRESSURE CURVES from the unit s SER VICE FACTS to determine the unit refrigerant charge The correc...

Page 23: ...place and properly fastened Has the owner been instructed on the proper operation and maintenance of the unit Be sure to leave this manual with the owner Final Installation Checklist 1 Check to make s...

Page 24: ...a 10 minute delay from the time of 1st stage ignition Comfort Control satisfied R and W1 W2 jumped contacts open signaling the control module to close the gas valve and de energize the induced draft b...

Page 25: ...not store combustible materials gasoline or other flammable vapors or liquids near the unit WARNING Owner Maintenance Some of the periodic maintenance functions of the packaged unit can be performed b...

Page 26: ...2 through 7 above Take care that all gaskets seat properly 12 Check all wires for correct installation by referring to the unit s electrical wiring diagram in the SERVICE FACTS 13 Leak test all gas li...

Page 27: ...3 Flashes Pressure switch problem detected Fast Flash Rate Not used 4 Flashes High Limit switch protection device open Steady ON Normal No Call for Heat 5 Flashes Flame sensed and gas valve not energi...

Page 28: ...com The AHRI Certified mark indicates company participation in the AHRI Certification program For verification of individual certified products go to ahridirectory org The manufacturer has a policy o...

Reviews: