Installation / Preparation for commissioning
Printed in the Federal Republic of Germany
TR-Electronic GmbH 2008, All Rights Reserved
06/19/2012
TR - ECE - BA - DGB - 0068 - 01
Page 67 of 109
5.2 Connection
Pin 1
PROFIBUS Data A
Pin 2
PROFIBUS Data B
Pin 3
PROFIBUS Data B
Pin 4
PROFIBUS Data A
Pin 5
1. Preset_IN,
11…27 V DC
Pin 6
2. Preset_IN,
11…27 V DC
Pin 7
Supply Voltage
, 11…27 V DC
Pin 8
0V, GND
Pin 9
0V, GND
Pin 10
Supply Voltage
, 11…27 V DC
For the supply shielded cables with twisted core pairs have to be used!
5.3 Bus termination
If the measuring system is the last slave
in the PROFIBUS segment, the bus is
to be terminated with the termination
switches S1 and S2 = ON. In this state,
the
subsequent
PROFIBUS
is
n’t
decoupled!