Central remote controller
Owner’s Manual
39
-EN
Setting the Operating Schedule
1
In the “All” screen, press [
] (Menu).
The “Settings Menu” screen is displayed.
2
In the “Settings Menu” screen, select “Schedule settings” and
then press [
] (Confirm).
The “Schedule settings” screen is displayed.
3
Select “Operating Sch settings” using [
∧
] and [
∨
], and then
press [
] (Confirm).
The “Select Zone” screen is displayed.
4
Select the zone to set using [<], [
∧
], [
∨
], and [>], and then press
[
] (Confirm).
The “Weekly display” screen of the selected zone is displayed.
5
Press [
] (Control).
The “Weekly Schedule” screen is displayed.
• In the “Weekly display” screen, you can make the Operating
Schedule void or set the unit to operate according to the special day
schedule.
• You can set dates for up to 5 weeks ahead.