GX9 ASD Quick Start Guide
Installation Precautions
Location and Ambient Requirements
•
The TIC ASD is intended for permanent installations only.
•
Installation shall conform to the
National Electrical Code
(NEC)
— Article 110
(
Requirements
For Electrical Installations
), all regulations of the
Occupational Safety and Health
Administration
, and any other applicable national, regional, or industry codes and standards.
Note:
For ALL references to the National Electrical Code (NEC), see the latest release of
the National Electrical Code.
•
Select a mounting location that is easily accessible, has adequate personnel working space, and
adequate illumination for adjustment, inspection, and maintenance of the equipment (refer to the
NEC Article 110-13).
•
DO NOT
mount the ASD in a location that would produce catastrophic results if it were to become
dislodged from its mounting location (equipment damage or injury).
•
DO NOT
mount the ASD in a location that would allow it to be exposed to flammable chemicals or
gases, water, solvents, explosive/corrosive mists or gases, or other fluids.
•
Avoid installation in areas where vibration, heat, humidity, dust, fibers, metal particles, or sources
of electrical noise are present.
•
For NEMA 1 installations, the system shall not be exposed to direct sunlight.
•
Allow proper clearance spaces for installation. Do not obstruct the ventilation openings. Refer to
the section titled
Installation and Connections on pg. 11
for further information on ventilation
requirements.
•
The ambient operating temperature range of the
GX9 ASD
is 14° to 104° F (-10° to 40° C).
Mounting Requirements
•
Only
Qualified Personnel
shall install this equipment.
•
Install the unit in a secure and upright position in a well-ventilated area.
•
As a minimum, the installation of the equipment shall conform to the
NEC — Article 110
(NEC),
OSHA, as well as any other applicable national, regional, or industry codes and standards.
•
Installation practices shall conform to the latest revision of NFPA 70E Electrical Safety
Requirements for Employee Workplaces.
•
It is the responsibility of the ASD installer/maintenance personnel to ensure that the unit is installed
into an enclosure that will protect personnel against electric shock.
Summary of Contents for GX9 ASD
Page 1: ...GX9 ASD Quick Start Guide TOSHIBA GX9 ASD Quick Start Guide DN 66900 001 March 2014 ...
Page 2: ......
Page 3: ...Document Number 66900 001 March 2014 GX9 ASD Quick Start Guide ...
Page 4: ......
Page 88: ...78 GX9 ASD Quick Start Guide Figure 33 GX9 ASD 5 0 20 HP Enclosure ...
Page 89: ...GX9 ASD Quick Start Guide 79 Figure 34 GX9 ASD 25 75 HP Enclosure ...
Page 90: ...80 GX9 ASD Quick Start Guide Figure 35 GX9 ASD 100 200 HP Enclosure ...
Page 91: ...GX9 ASD Quick Start Guide 81 Figure 36 GX9 ASD 250 400 HP Enclosure ...
Page 92: ...82 GX9 ASD Quick Start Guide Figure 37 GX9 ASD 500 800 HP Enclosure ...
Page 93: ...GX9 ASD Quick Start Guide 83 Figure 38 GX9 ASD 900 1200 HP Enclosure ...