13 UPS Operation
The 4400 UPS is hardwired to both utility power and the critical loads. The two main operating states are :
1. On-Line (double conversion) mode with the UPS providing clean power to the load.
2.
Bypass mode, where the unconditioned utility power is routed around the converter-inverter of the UPS and
fed directly to the load.
A third state, Emergency shut-down,
EPO, is for emergency use only and is discussed separately in Section 12.3.
The UPS can be switched between On-Line and Bypass by pressing and momentarily pressing the RUN/STOP button on
the touchscreen display.
13.1 Standard UPS Operation (No Internal MBS)
Initial UPS Startup
The first time the UPS is started after installation, use the touchscreen to enter the current time and date.
1. Start the UPS as described in 13.2 steps 1-5.
2.
Enter the
System Date
:
Press the
Setup
tab.
Press
System Date
in the Data Display Area.
Enter the date in the following format:
Www
Mmm DD YYYY
Www
is the three character day of the week: Mon, Tue, Wed...
Mmm
is the three character Month: Jan, Feb, Mar...
DD
is the two digit day of the month: 01, 12, 30...
YYYY
is the four digit year: 2011
Press
Write
to store the date.
Press
Quit
to exit
System Date
setup.
3.
Enter the
System Time
:
Press the
Setup
tab.
Press
System Time
in the Data Display Area.
Enter the Time in the following format:
HH:MM AM
HH
is the two digit hour followed by a colon (:)
MM
is the two digit month.
AM/PM
is before or after noon.
Press
Write
to set the time.
Press Quit to exit System Time setup.
Summary of Contents for 4400 Series
Page 2: ......
Page 6: ...This page left intentionally blank ...
Page 10: ...This page left intentionally blank ...
Page 136: ...This page left intentionally blank ...
Page 137: ......