4: INSTALLATION
7. Lift the machine frame enough to clear the crate and use
a pallet jack to remove the crate from the area.
4.4.2 Installing Legs and Righting Machine
1. Lower the bottom end of the frame down on to 4x4
blocks to protect the paint and clear the engine hoist
legs (if present).
2. Install the top two legs on the machine on the end
supported by the lifting sling.
3. Using gantry crane, slowly lower the top side of the
machine frame until the two legs are on the ground.
4. Move the lifting sling to the same position on the
opposite end of the frame.
5. Lift the remaining end of the frame off of the 4x4 blocks.
6. Remove the two nuts (used to bolt to the crate frame)
from inside the leg mounting holes. Do not discard the
socket head cap screws attaching the nuts, these are
used to attach the last two legs.
7. Install the last two legs.
4.5 LEVEL THE MACHINE FRAME AND WATER
TABLE
Tools and Items Required
l
Carpenter's Level
l
Crescent Wrench
l
Allen Key
The water table can be leveled at any time, but it is easiest to
do before the side panels have been installed.
©Tormach® 2020
Specifications subject to change without notice.
Page 29
UM10720: 1300PL Operator's Manual (Version 0820B)
For the most recent version, see tormach.com/support
Summary of Contents for 1300PL
Page 1: ...Original Instructions OPERATOR S MANUAL Version 0820B ...
Page 10: ......
Page 24: ......
Page 50: ......
Page 58: ......