Setting up the Machine and 3DMC
mmGPS 3D Paver Reference Manual
3-8
Power Switch
The power switch (Figure 3-4) turns on the control
box, as well as the sensors installed on the machine. After a few
moments, the 3DMC software appears on the touch screen display
and is ready to use.
Figure 3-4. Power Switch
The control box saves and stores previous settings, elevation offsets,
and the cross-slope calibration. Upon power-up, the 9168 control box
applies these settings, offsets, and calibrations. Except for variable
day-to-day measurements of the receiver and the screed, you can use
saved calibrations and adjustments for several weeks or months.
Connectors
The connectors (Figure 3-5) supply power to the mmGPS 3D Paver
machine and link system sensors and components installed on the
machine with the 9168 control box.
Figure 3-5. 9168 Control Box – Connectors
Depending on your control application, the connectors used during
operation varies.
ON
OFF
A
Power I/O Bus
B
Valves
C
RS485 Port/Valves
D
RS232 Port
Summary of Contents for mmGPS 3D Paver
Page 1: ...MM 03 0AVER 2EFERENCE ANUAL...
Page 2: ......
Page 4: ...ECO 3067...
Page 34: ...Introduction mmGPS 3D Paver Reference Manual Notes 1 20...
Page 70: ...Setting up the Jobsite and Pocket 3D mmGPS 3D Paver Reference Manual Notes 2 36...
Page 208: ...Getting Started mmGPS 3D Paver Reference Manual Notes 5 32...
Page 252: ...Safety Information mmGPS 3D Paver Reference Manual Notes A 4...
Page 278: ...Glossary mmGPS 3D Paver Reference Manual Notes E 6...
Page 285: ...Index P N 7010 0781 Index definition 3 23 display options 3 25...
Page 286: ...mmGPS Paver 3D Reference Manual Notes Index...
Page 287: ......