102
NV021 - Manual - 08 - 2012
SETTING AND COMMISSIONING
7.4 MAINTENANCE
The Pro_N relays do not require any particular maintenance; all circuits use high quality static com-
ponents, the subassembly products undergo dynamic checks on their functioning before the fi nal
assembling of the complete equipment. The dedicated circuits and the fi rmware for the self-test
function continuously check the relay operation; the continuously operating auto-zeroing function
dynamically corrects the measuring errors due to offset, heat dependent drifts, aging of components,
etc.
The microprocessor is equipped with a watch-dog circuit which restores the correct operation of
the fi rmware in case of fault.
The possibility of reading the value of the signals measured on the display (the NV10 relay used as an
ammeter) allows one to check both the system parameters and the operation of the protection relays
at any time. The NV10 relay can be preset as well to show the current values referred to the nominal
current of the current transformers, as directly in primary amperes (according to the preset value of
CT’s nominal primary current); the same is done for the input voltages.
If connected to the central control unit, all data available on the display can be checked and pro-
cessed thus performing a continuous check and maintenance.
7.5 REPAIR
No repair of possible faults by the client is foreseen; if following to any irregularity of operation, the
above tests confi rm the presence of a fault, it will be necessary to send the relay to the factory for
the repair and the consequent settings and checks.
7.6 PACKAGING
The Pro_N devices must be stored within the required temperature limits; the relative humidity should
not cause condensation or formation of frost.
It is recommended that the devices are stored in their packaging; in the case of long storage, espe-
cially in extreme climatic conditions, it is recommended that the device is supplied with power for
some hours before the commissioning, in order to bring the circuits to the rating conditions and to
stabilize the operation of the components.