18. Two reels of foam tape (P) are provided (one per HEPA FFU). Cut each reel into two 600mm [23.6”] lengths and two
1180mm [46.5”] lengths, giving a total of four of each length.
19. Taking each strip of foam tape in turn, remove the adhesive backing and stick the lengths of tape to the top of the
flanges. Stick the 600mm lengths first on top of the short flanges. Stick the 1180mm lengths on top of the long flanges.
Do not overlap the foam.
Figure 18 Roof Frame Assembly (One Side Only Shown) – Step 19
20. Set the spacing of the low profile screws (as per step 2) in both ends of the 2x Long Top Cross Members (D
).
Figure 19 Roof Frame Assembly – Step 20
Set the completed Roof Assembly to one side.