Antaris EX-Z2 Specifications
Floor mounting
Optionally, a system may be mounted to the floor. The floor must be
capable of supporting two times the weight of the instrument and floor
stand.
In this configuration, the wall-mount flanges may be removed.
The instrument must be accurately secured within 2 degrees of vertical.
The floor used for mounting must be within 2 degrees of level for proper
operation.
All fasteners, brackets, and bolts are required to safely secure the instrument
to the stand. For anchoring the enclosure, we recommend using high
quality steel 10 mm (3/8 in) bolts that are capable of withstanding the
following forces:
Force
Specification
Shear force
250 N (56 lb)
Tensile force
300 N (68 lb)
Pull-out force
30 N (68 lb)
Thermo Fisher Scientific
Antaris EX Safety, Installation, and Site Preparation Guide
93