24
First operating
7
First operating
To complete the start-up of the boiler, the
following operations are necessary, that should
only be performed by an authorized Technical
Assistance Centre:
Verification of the installation;
Slave board setting
Combustion analysis;
7.1
Slave board setting
This operation that should only be performed
by an authorized Technical Assistance Centre.
Each slave unit that composes the system
should be identifiable from the only master
board, through an address that is assigned
properly configuring the switches J10 and J17,
on each slave battery. Each slave (one for each
burner) needs to be properly configured so
that the Master board shall detect their right
sequence.
The slaves are divided into blocks of four slave
each (every Corolla Pack is a block) and the
system can handle up to 15 blocks. Therefore,
the address configuration is done for each slave
using the following procedure, always remem-
bering that a block is equivalent to a pack:
Locate the block the slave is related to (ex.
Block n°1, n°2…………till block n°15);
Locate the slave position inside each block
( e.g. position1,2,3 or 4);
Supply each Corolla Pack composing the
battery (see par.6.4.1)
All electrical maintenance and installing
operation have to be made in full compliance
with the applicable Law and with the instruc-
tions provided by the Manufacturer, and will
always be carried out by professionally quali-
fied technical personnel only, with particular
attention to safety standards.
As shown in Figure 20 to set the address of the
block you should work on the switch located on
the right (Jumper J17) and for each slave (sin-
gle burner) on the Left one (Jumper J10.
Figure 20
Refer to Table 2 to see the possible combina-
tions of the jumpers J10 that characterize the
four slaves (n 1, 2, 3 and 4) of the same block.
Table 3 shows the possible combinations of the
jumpers (J17) we have the settings for the
maximum (15) number of block.
JUMPER J10
SLAVE ADDRESS
1
2
OFF
OFF
1
OFF
ON
2
ON
OFF
3
ON
ON
4
Table 2
Summary of Contents for COROLLA PACK 1000 Series
Page 1: ...COROLLA PACK SERIE1000 ...
Page 2: ......
Page 35: ...35 Electrical wiring diagram ...
Page 38: ...NOTES ...
Page 39: ......
Page 40: ...20135201 Rev 0 05 17 ...