TemperZone OPA 330RKT Installation & Maintenance Download Page 1

OPA 330RKT

Packaged Reverse Cycle R410A

Air Cooled Air Conditioner

GENERAL

This OPA 330RKT unit must be installed 
in accordance with all national and local 
safety codes.

CONFIGURATIONS

The OPA 330RKT is supplied in one of two 
standard configurations :
1.  Horizontal supply/return air with box 

mounting channel (RKTH), or

2.  Downward supply air with box mounting 

channel (RKTU).

REFRIGERATION SySTEm
General

The refrigeration system has been charged 
with 9.7 kg each of HFC-410A (R410A) 
refrigerant. Tapping points are provided to 
measure discharge and suction operating 
pressures.  

Compressors

The compressor is directional scroll 
type. The compressor lubricant is polyol 
ester oil (POE). Note, this oil absorbs 
moisture quickly if exposed to open air. On 
commissioning, the compressor must be 
checked for correct rotation (refer Start Up 
Procedure).

ECONOmISER (Option)

If the outdoor air heat content or 
temperature is below that of the return 
air, the fresh air damper opens and the 
return air damper closes to provide the first 
stage of cooling.  The compressor will then 
operate to provide more cooling if required. 

INSTALLATION

Unpacking

Units configured with Downward supply air 
and mounting rails, have their spigots
shipped loose inside the return air cavity.

Positioning

Refer to dimension diagrams for minimum 
clearances. If multiple units are to be 
placed side-by-side then allow at least 2 m 
between coil faces.

mounting

The unit should be fastened to a firm flat 
horizontal base using the holes supplied in 
the box mounting channel.

When the unit is being installed on a roof 
it is recommended that the unit is installed 
on a substantial structure with vibration 
isolating springs beneath the unit. These 
springs are not supplied with the unit.

Installation & 

maintenance

Flexible duct connections are recommended 
between the supply and return ducts and 
the unit.

Condensate Drain

The condensate drain should be 'U' trapped 
outside the unit. The trap should have a 
Downward height of at least 100 mm. The 
drain should have a slope of at least 1 in 50 
and must not be piped to a level above the 
unit drain pipe (see figure 3).

Electrical Requirements

Electrical work must be done by a qualified 
electrician.  The outdoor unit must be wired 
directly from a distribution board by means 
of a circuit breaker or H.R.C. fuse, and a 
mains isolator provided - preferably close to 
the unit.

Note

:  DO NOT USE REWIRABLE FUSES.

The OPA 330 is provided with a 24V AC 
control circuit for a thermostat, on/off switch 
and/or time clock.

The control transformer 240V primary 
voltage is used for countries with 230-240V 
power supply. For countries with supply 
voltages 200-220V, change the primary 
voltage on the transformer to 208V.

Standard units are suitable for use with 
thermostats with either manual Heat/Cool 
selection or automatic changeover subject to 
the contact ratings of the thermostats. 

A 24 hour power supply to the compressor 
crank case heater is required, otherwise the 
warranty is void.

CHECK TESTS

1. Leave the on/off switch in the off position 

and close the mains isolating switch.  
A four hour delay period is required to 
allow the crankcase heaters to drive any 
liquid refrigerant out of the compressor oil.

2. Check that the shipping block beneath the 

compressor has been removed and that 
the compressor is secure on its mounts.

3. Check that all fan motors are free running.
4. Check that the thermostat is correctly 

wired to the unit and is set at the desired 
temperature.

5. Check that the air filters have been 

correctly installed if fitted.

6. Check air diffuser dampers are open if 

appropriate.

START UP PROCEDURE

Use the supplied Commissioning Sheet to 
help you complete the following procedure:
1. After the four hour delay period has 

expired, switch on the unit.

2. The compressor fitted is directional. 

Check for correct rotation. If rotation is 
incorrect the compressor will not pump, 
be noisy, and will draw minimal current. 
To correct motor rotation, change the 
phasing at the main power terminal. If 
changing the phasing, check the indoor 
air fan then runs in the correct direction 
also.

3. Check the supply voltage between each 

phase and neutral.

4. Measure the current draw on each phase 

to the compressor motor and measure the 
current draw of each fan motor. Check all 
readings against the specified values in 
the wiring diagram.

5. Fit gauges and measure the suction and 

discharge pressures of both refrigeration 
circuits.

6. Check that the outdoor air fan motors are 

running smoothly.

7. Test the operation of the reversing valve 

by running the unit in both the heating 
and cooling mode.

8. Check the indoor unit's fan belt tension 

after 20 mins of operation and adjust if 
necessary (refer Commissioning Sheet).

9. Check the supply air flow at each outlet.
10.Check the tightness of all electrical 

connections and sign the check label.

11.Touch up any outdoor unit paintwork 

damage to prevent corrosion.

SETTING SUPPLy AIR FLOW

Consult OPA 330 Technical Data pamphlet 
for details of airflow/duct static pressure, if 
required. 
If the indoor air returning to the unit is 
regularly expected to be above 50%RH, 
then the coil face velocity should be limited 
to be 2.5 m/s or less (refer Air Handling 
graph in Technical Data pamphlet). 
High humidity levels can occur in tropical or 
subtropical conditions, and/or when heavily 
moisture laden fresh air is introduced. 
Select a fan speed that avoids water carry-
over problems.
In a free blow or low resistance application,  
beware of exceeding the fan motor's full 
load amp limit (refer wiring diagram).
The indoor air fan motor is fitted with 
a factory set adjustable pitch pulley. 
Instructions for the adjustment of pulleys is 
included on the back page of the supplied 
Commissioning Sheet. One revolution of 
adjustment is equal to approx. 7% change 
in air volume flow rate.  

Reviews: