TemperZone OPA 2000RKTM01 Installation & Maintenance Download Page 1

OPA 2000RKTM01
Packaged Reverse Cycle R410A

Air Cooled Air Conditioner

GENERAL

This OPA 2000RKTM Outdoor Unit must be 

installed in accordance with all national and 

local safety codes.

REFRIGERATION SYSTEM

General

The OPA 2000 has four independent 

refrigeration circuits and four compressors 

to provide the flexibility and economy of 

four stage operation, i.e. utilising one or 

more circuits as conditions vary, plus the 

advantage of staggered starting.
Each refrigeration system has been charged 

with HFC-410A (R410A) refrigerant; refer 

wiring diagram specification table for 

amount. Tapping points are provided to 

measure discharge and suction operating 

pressures.  

Compressors

The compressors are directional scroll 

type. The compressor lubricant is polyol 

ester oil (POE). Note, this oil absorbs 

moisture quickly if exposed to open air. 

On commissioning, the compressors must 

be checked for correct rotation (refer Start 

Up Procedure). A time delay prevents 

simultaneous starting of the compressors.

ECONOMISER (Option)

If the outdoor air temperature or heat 

content preferably, is below that of the return 

air the fresh air damper opens and the return 

air damper closes to provide the first stage 

of cooling. A spill air facility in the building 

may be necessary for when the return air 

damper is closed. The fresh air damper 

should return to minimum setting and the 

return air damper open before compressors 

are allowed to operate to provide further 

cooling.  

INSTALLATION
Positioning

Refer to dimension diagrams for minimum 

clearances. If multiple units are to be placed 

side-by-side then allow at least 2 m between 

coil faces.

Mounting

The unit should be fastened to a firm flat 

horizontal base using the holes supplied in 

the mounting channels.
When the unit is being installed on a roof it 

is recommended that the unit is installed on 

a substantial structure with vibration isolating 

springs beneath the unit. These springs are 

not supplied with the unit. 
Flexible duct connections are recommended 

between the supply and return ducts and 

the unit.

Installation & 

Maintenance

Condensate Drain

The condensate drain should be 'U' trapped 

outside the unit. The trap should have a 

vertical height of at least 100 mm. The drain 

should have a slope of at least 1 in 50 and 

must not be piped to a level above the unit 

drain pipe.

Electrical Requirements

Electrical work must be done by a qualified 

electrician.  The outdoor unit must be wired 

directly from a distribution board by means 

of a circuit breaker or H.R.C. fuse, and a 

mains isolator provided - preferably close to 

the unit.

Note:  DO NOT USE REWIRABLE FUSES.
The OPA 2000 is provided with a 24V AC 

control circuit for a thermostat, on/off switch 

and/or time clock.
The control transformer 240V primary 

voltage is used for countries with 230-240V 

power supply. For countries with supply 

voltages 200-220V, change the primary 

voltage on the transformer to 208V.
Standard units are suitable for use with 

thermostats with either manual Heat/Cool 

selection or automatic changeover subject 

to the contact ratings of the thermostats. 
A 24 hour power supply to the control circuit 

is required, otherwise the warranty is void.

CHECK TESTS

1. Check that the shipping block beneath the 

compressor has been removed and that 

the compressor is secure on its mounts.

2. Check by hand that all fan motors can 

turn freely. 

3. Check that the air filters have been 

correctly installed, if fitted.

4. Check air diffuser dampers are open if 

appropriate.

5. Check that the thermostat, or external 

24V controller, is correctly wired to the 

unit and is set at the desired temperature.

6. Check the tightness of all electrical 

connections and sign the check label.

7. Leave the thermostat, or external 24V 

controller, in the off position and close the 

mains isolating switch. (A four hour delay 

period is required to allow the crankcase 

heater to drive any liquid refrigerant out of 

the compressor oil.)

8. Check the supply voltage between each 

phase and neutral.

START UP PROCEDURE

After the four hour delay for the crankcase 

heater has expired, use the supplied 

Commissioning Sheet (Form NS 228) to 

record results when completing the following 

‘Start-up’ procedure. A UC6 Service 

Interface tool is supplied to read, pressures, 

superheat and its set-point, compressor 

amps etc.

1. Select a sensible Fan speed (or Auto Fan 

mode), operating cycle (cool or heat), and 

room temperature set point, depending on 

the time of year, such that the compressor 

will start and run at a high capacity.

2. Turn ON the thermostat / External 

controller. Wait for the compressors to 

start. 

3. Compressors fitted are directional. Check 

for correct rotation. If rotation is incorrect 

the compressor will not pump, be noisy, 

and will draw minimal current. To correct 

motor rotation, change the phasing at 

the main power terminal. If changing the 

phasing, check the indoor air fan then 

runs in the correct direction also.

3. Measure the current draw on each phase 

to the compressor motors and measure 

the current draw of each fan motor.  

Check all readings against the specified 

values in the wiring diagram.

4. Use the UC6 Service Interface tool  to 

check operating pressures and status. If 

the UC6 Service Interface is not available, 

fit gauges and measure the suction and 

discharge pressures of both refrigeration 

circuits. 

5. Check that the outdoor air fan motors are 

running smoothly and drawing less than 

the full load amps specified.

6. Test the operation of the reversing valve 

by running the unit in both the heating 

and cooling mode.

7. Check the supply air flow at each outlet.

8. Touch up any outdoor unit paintwork 

damage to prevent corrosion.

SETTING SUPPLY AIR FLOW

Consult OPA 2000 Technical Data pamphlet 

at www.temperzone.biz for details of airflow/

duct static pressure, if required. 
If the indoor air returning to the unit is 

regularly expected to be above 50%RH, 

then the coil face velocity should be limited 

to be 2.5 m/s or less (refer Air Handling 

graph in Technical Data pamphlet). 
High humidity levels can occur in tropical or 

subtropical conditions, and/or when heavily 

moisture laden fresh air is introduced. 

OPEN

DRAIN

MINIMUM

SLOPE

20 mm PER m

(1 IN 50)

100 mm

MINIMUM

200 mm

APPROX.

'U' TRAP

100 mm

APPROX.

VENT PIPE

FOR LONG

CONDENSATE

DRAIN RUNS

Reviews: