2-31
Installation
12. Refer to
. Connect the two large black cables running down from
the right rear of the Signal Processor Frame to the right (Pioneer) or bottom
(Todd) stud. If you are only installing a primary supply, secure with the nut
and lock-washer removed previously. Torque the nut to 80 inch/pounds (6.67
foot
/pounds) +/- 5%.
13. Connect the two large red cables running down from the right rear of the
Frame to the left (Pioneer) or top (Todd) stud. If your are only installing a
primary supply, secure with the nut and lockwasher removed previously.
Torque the nut to 80 inch/pounds (6.67 foot/pounds) +/- 5%.
14. Ensure that the power cables are properly positioned in the slot cut out of the
Power Supply.
15. At the left rear of the Power Supply, thread the two connectors through the
rectangular cutouts in the power supply and connect them to the jacks that are
installed in the bottom rear channel of the frame. The connectors are keyed for
proper alignment.
Black Cables from
Signal Processor
Frame.
Connectors attached
to bottom rear channel
of Frame. Located directly
above the power supply.
Red Cables from
Signal Processor
Frame.
Black Cables from
Signal Processor
Frame.
Red Cables from
Signal Processor
Frame.
TODD SUPPLY
PIONEER SUPPLY
0621-01-05
Figure 2-19. Frame Power Supply Connections.
Summary of Contents for Grass Valley 4000
Page 3: ...iii Tektronix Grass Valley Products P O Box 1114 Grass Valley CA 95945 916 478 3800 ...
Page 4: ...iv Tektronix Grass Valley Products P O Box 1114 Grass Valley CA 95945 916 478 3800 ...
Page 34: ...1 20 Section 1 System Overview ...
Page 138: ...2 104 Section 2 Installation ...
Page 196: ...3 58 Section 3 Functional Description ...
Page 286: ...Index 6 Index ...