4.10 Control Module panel test functions and alarms
LED
Description
Instruction
BATTERY TEST
As a basic setting, the battery test is done
automatically twice a year: on the 4
th
of July
and on the 4
th
of January, at 12 pm (midnight).
If the LED is continuously lit, the battery
test is in progress.
If the LED is flashing, an error has been
detected in the battery test. In this case
the
External fault
LED will also be lit.
During the battery duration test, the central
battery unit is switched to battery mode and
all output circuits are switched on.
If the LEDs
Internal fault
is lit and
Battery
test
is flashing, the battery duration test
has failed.
A change of battery always requires a new
configuration, so that the software knows a
battery has been replaced.
The battery test can be started by pressing
one button on the control unit interface, or
manually using the control unit menu.
No action needed, unless the test
fails. If the test fails check condition
of batteries
To run the battery test yourself,
either
1. Press the
BROWSE
button for
8 seconds.
or
1. Press the
MENU / OK
button.
2. Use the
BROWSE
button to
select 2,
TESTING.
3. Use the
SET
button to select 3,
battery test during 2/3 of the
operation time.
4. Accept the selection with the
MENU / OK button.
The battery test starts.
LUMINAIRE TEST
If the LED is continuously lit, the luminaire test
is in progress.
If the LED is flashing with
External fault
LED,
configuration is in progress.
Luminaire test must be carried out once in 1-7
days. Factory setting is once a day at
midnight (00.00 o’clock).
No action needed, unless the test
fails. If the test fails check condition
of luminaires.
To run the luminaire test yourself,
either
1. Press the
BROWSE
button for
3 seconds.
or
1. Press the
MENU / OK
button.
2. Use the
BROWSE
button to
select 2,
TESTING.
3. Use the
SET
button to select 1 =
Starting the luminaire test.
4. Accept the selection with the
MENU / OK button.
The luminaire test starts. If a faulty
luminaire was found in any of the
circuits, its corresponding LED will
Summary of Contents for TKT66
Page 40: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 40 TKT66 P...
Page 43: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 43...
Page 44: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 44...
Page 45: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 45...
Page 46: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 46...
Page 47: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 47...
Page 48: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 48...
Page 49: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 49...
Page 50: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 50...
Page 51: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 51...
Page 53: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 53...
Page 54: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 54...
Page 55: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 55...
Page 56: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 56...
Page 57: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 57...
Page 58: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 58...
Page 59: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 59...
Page 60: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 60...
Page 61: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 61...