© 2014 UTC Fire & Security Australia Pty Ltd. All rights reserved.
1 / 2
P/N MAINST-TS1021 • REV 03 • ISS 08AUG14
Eight-Input Expansion Module Installation Sheet
Description
Eight-Input Expansion Modules add eight inputs to TS0820,
TS0824, TS0866 and TS1020 DGPs.
This Installation Sheet applies to models TS0021 and TS1021
expansion modules:
•
TS0021 expansion modules (green PCB) may be used
with Challenger10-series TS1020 Analogue DGPs, and
with Challenger V8-series TS0820, TS0824, and
TS0866 Data Gathering Panels (DGPs).
•
TS1021 expansion modules (blue PCB) may be used with
Challenger10-series TS1020 Analogue DGPs.
Figure 1: Eight-Input Expansion Module
1. Configuration DIP switch
2. J2 connector for ten-way cable from DGP or from previous
expansion module
3. J3 connector for ten-way cable to next expansion module
4. Input terminals
Expansion modules have a pair of ten-way connectors, and
one cable. One module can be plugged into a DGP’s J7
connector, and two additional modules can be daisy-chained to
the first, subject to the following:
•
TS0820, TS0824, and TS1020 DGPs have eight onboard
inputs. Up to three expansion modules can be daisy-
chained to increase the quantity of inputs to 32.
•
TS0866 Intelligent 4-Door Controllers have eight onboard
inputs. One TS0021 module can be used to increase the
quantity of inputs to 16.
The added inputs are numbered according to “Input
numbering” on page 2.
Product contents
Quantity Item
1
Eight-Input Expansion Module with ten-way cable
1
Installation Sheet
1
Ring terminal
4
Three-way plug-on screw terminal connectors
5
M3 x 10 mm pan head screws
4
PCB standoffs
18
10 kΩ 1/4 W resistors
Inspect the package and contents for visible damage. If any
components are damaged or missing, do not use the unit;
contact the supplier immediately. If you need to return the unit,
you must ship it in the original box.
Installation
Expansion modules are mounted on standoffs (supplied) using
M3 x 10 mm pan head screws (supplied) inside the DGP
enclosure. The PCB is size B.
NOTICE!
A qualified service person, complying with all
applicable codes, should perform all required hardware
installation.
To install the module:
1. Disconnect the plug pack and battery from the DGP.
2. Insert four standoffs (supplied) into the DGP enclosure at
a location suitable for the ten-way cable to connect the
expansion module to the DGP, or other expansion
module, as needed.
3. Slide the board’s terminal connectors together and mount
on the board.
4. Use four M3 x 10 pan head screws to fix the module to the
standoffs.
5. Connect the ten-way cable to the J2 connector on the
expansion module.
6. Connect the ten-way cable to the J7 connector on the
DGP, or other expansion module, as needed.
7. Connect the required input cables to the input terminals.
See “Input wiring” on page 2.
8. Configure the expansion module’s three-segment DIP
switch, and (if applicable) the DGP’s DIP switch (see
“Configuration settings” on page 2).
9. Reapply power to the DGP.