4 - 10
Balance Kit Operating Manual, 393278, en, V1.0
4 - Putting into Operation
Setting up the Balance Kit and the SAG 285/01
4.1.10 Getting Ready for the Gravimetric Test
Now the last steps before the Gravimetric Test can be carried out.
Procedure
To make the installation ready for the Gravimetric Test:
1
If not done yet, place the adapter plate (G) with the installed Weighing Cell (H)
on the worktable in the grid position that corresponds to the worktable map.
2
Place the evaporation ring (B) on the Weighing Cell.
3
Place the vessel (C) on the weighing pan (E).
4
Carefully fill the evaporation ring with distilled or de-ionized water until the ring
is about half-full.
ATTENTION
Damage to Weighing Cell possible if liquid is spilled over the cell.
Be careful not to fill up the ring too much, so that you can safely remove it
from or place it on the Weighing Cell without spilling any liquid.
Wipe up any spilled liquid with a soft lint-free cloth.
5
Cover the evaporation ring and the parts inside it with the draft shield (A).
The Gravimetric Test can now be carried out.
Fig. 4-7
Getting ready for the Gravimentric Test