5.1 No-load Tests
ATTENTION.
Before powering the main line, the OSM should be in the OPEN position. The OSM shall be
closed via the MMI only after the no-load tests are performed.
Powering the Protection Device
5.1.1
Switch on the battery switch. Make sure that local time and date are correct. If date, time or both are
incorrect
connect to the RC via USB, Bluetooth or TDI (see “6.5. Other RC5_4 Control Options” for details)
and synchronize date and time on your computer with the RTC of the RC using TELARM. Date and time is
visible at the MMI screen.
Date and time synchronization procedure:
TELARM->On-line->Synchronize date and time
Date and time setup via MMI:
CPM Main Menu -> Control Data -> Set Date and Time
After that the commissioning engineer should make sure that the MMI menu navigation is OK, indication on
the MMI is OK.
RC5 Power Supply Check
5.1.2
For each of the conditions described below check that MMI displays no errors and MMI LED function
(Lockout LED, Mode
– Local LED, State – Open LED, On or Off LED of each protection button, Active group
– 1 LED)
Battery switch is OFF, AC supply switch is ON;
Battery switch is ON, AC supply switch is OFF
9
;
Battery switch is ON, AC supply switch is ON.
NOTE:
Up to 60 s might be required for the RC5_4 circuits energizing.
Checking CVCS Coefficients
5.1.3
Check that the CVCS coefficients in the RC5_4 settings correspond to the RTC.
CVCS coefficient indications:
MMI -> Main menu -> Settings -> System -> Measurement
To correct coefficients, connect to the RC via TELARM:
TELARM -> On-line -> Rec -> System settings -> System -> ME settings
Change “Wires to terminal connection” setting. Check that all other System settings in TELARM are correct
for the particular device. How to upload settings is described in “6.6. Settings Modifications”.
Checking Phase Sequences
5.1.4
After powering the main line at the OSM OPEN state, the commissioning engineer should perform the
PHASE SEQUENCE check-up. The negative sequence voltage (U2) should be less than 1kV.
Negative voltage sequence indication:
MMI -> Main menu -> Indication data -> Measurement -> U2
If the negative sequence voltage is observed, it is recommended to change the software setting (changing
phase sequence System-Phase sequence).
Changing phase sequence:
TELARM -> On-line -> Rec -> System settings -> System -> Configuration -> Wires to terminal
connection
Change “Wires to terminal connection” setting. Check that all other System settings in TELARM are correct
for this particular device. How to upload the System settings is described in the “Operation” chapter.
9
If rechargeable battery is available.
Summary of Contents for Rec15/25 Al1 5p
Page 1: ......
Page 8: ......
Page 9: ...1 Product Description...
Page 15: ...15 Figure 11 CPM control and indication functions...
Page 25: ...2 Nameplates and Seals...
Page 29: ...3 Product Handling...
Page 42: ......
Page 43: ...4 Installation...
Page 57: ...5 Commissioning...
Page 60: ......
Page 61: ...6 Operation...
Page 78: ...78...
Page 79: ...7 Maintenance and Troubleshooting...
Page 93: ...8 Disposal...
Page 95: ...9 Appendices...
Page 98: ...98 Appendix 2 RC5_4 Drawings Figure 97 Dimensions of RC5_4...
Page 102: ...102 Figure 103 Dimensions of standard OSM mounting kit arrangement for lateral installation...
Page 103: ...103 Figure 104 Dimensions of interface bracket...
Page 104: ...104 Figure 105 Dimensions of OSM mounting kit with M16 pole interface front installation...
Page 105: ...105 Figure 106 Dimensions of OSM mounting kit with M16 pole interface lateral installation...
Page 106: ...106 Figure 107 Dimensions of OSM mounting kit with M20 pole interface front installation...
Page 107: ...107 Figure 108 Dimensions of OSM mounting kit with M20 pole interface lateral installation...
Page 118: ...118 Figure 119 Dimensions of OSM substation mounting kit...
Page 119: ...119 Figure 120 Dimensions of OSM substation mounting kit...
Page 122: ...122 Figure 123 Dimensions of RC mounting kit for through the pole installation...
Page 123: ...123 Figure 124 Dimensions of RC substation mounting kit...
Page 124: ...124 Figure 125 Dimensions of VT mounting kit One VT holder...
Page 132: ...132 Appendix 5 RC5_4 Wiring Diagram Figure 139 RC5_4 wiring diagram...
Page 135: ...135...
Page 136: ......