44
Installation operations are carried out by utility technical personnel and can be supervised by Tavrida electric
technical representatives. This chapter describes installation procedures and required equipment. For more
detailed information about the installation process contact a Tavrida electric technical representative.
Additionally, there is a walkthrough installation video available on Youtube:
https://www.youtube.com/watch?v=hkPAtRW8FkQ&
4.1 Required Equipment
1. Set of wrenches (8-24mm);
2. Set of screw drivers (+ and - );
3. Screw driver “-” 2.5x0.4 for WAGO terminals;
4. Diagonal pliers;
5. Power line connection provision:
Wires (preferable insulated) (6 pcs.);
Support insulators 3 pcs. (if required);
Cable lugs applicable for chosen connection wires and M12 bolt (6 pcs.);
Connection clamps (waterproof if insulated connection wires are used) (6 pcs.).
6. Hydraulic cable terminal lug manual clamp up to 240mm2;
7. Alcohol for insulation cleaning;
8. Crane or other lift for OSM and RC5_4 lifting.
4.2 Installation Procedure
WARNING!
This User Guide is offered as a guide only. It should be used in conjunction with the utility’s own
safety procedures. Before installation begins, all necessary precautions should be carried out.
OSM Installation
4.2.1
Before starting the OSM installation, make sure that:
The OSM main contacts are open,
The control cable is disconnected,
The OSM control cable socket cover is closed.
The mounting kit and surge arresters (depending on particular installation) should be installed according to
procedure described in the Handling and Installation guide.
The OSM installed on the mounting frame should be lifted as shown in Figure 33.
ATTENTION!
The HV assembly lifting facilities should not come into contact with bushings, surge arresters
or auxiliary VT bushing extensions.
ATTENTION!
When installing the HV assembly, make sure that the connection to the line is performed
according to the procedure described in the Handling and Installation guide.
Summary of Contents for Rec15/25 Al1 5p
Page 1: ......
Page 8: ......
Page 9: ...1 Product Description...
Page 15: ...15 Figure 11 CPM control and indication functions...
Page 25: ...2 Nameplates and Seals...
Page 29: ...3 Product Handling...
Page 42: ......
Page 43: ...4 Installation...
Page 57: ...5 Commissioning...
Page 60: ......
Page 61: ...6 Operation...
Page 78: ...78...
Page 79: ...7 Maintenance and Troubleshooting...
Page 93: ...8 Disposal...
Page 95: ...9 Appendices...
Page 98: ...98 Appendix 2 RC5_4 Drawings Figure 97 Dimensions of RC5_4...
Page 102: ...102 Figure 103 Dimensions of standard OSM mounting kit arrangement for lateral installation...
Page 103: ...103 Figure 104 Dimensions of interface bracket...
Page 104: ...104 Figure 105 Dimensions of OSM mounting kit with M16 pole interface front installation...
Page 105: ...105 Figure 106 Dimensions of OSM mounting kit with M16 pole interface lateral installation...
Page 106: ...106 Figure 107 Dimensions of OSM mounting kit with M20 pole interface front installation...
Page 107: ...107 Figure 108 Dimensions of OSM mounting kit with M20 pole interface lateral installation...
Page 118: ...118 Figure 119 Dimensions of OSM substation mounting kit...
Page 119: ...119 Figure 120 Dimensions of OSM substation mounting kit...
Page 122: ...122 Figure 123 Dimensions of RC mounting kit for through the pole installation...
Page 123: ...123 Figure 124 Dimensions of RC substation mounting kit...
Page 124: ...124 Figure 125 Dimensions of VT mounting kit One VT holder...
Page 132: ...132 Appendix 5 RC5_4 Wiring Diagram Figure 139 RC5_4 wiring diagram...
Page 135: ...135...
Page 136: ......