Installation – Commissioning – Maintenance

20150101

Installation

Size of opening, see the dimension print. Place the 
mounting frame in the opening and secure it with screws 
to the building structure. Rotate the diffuser face to 
engage it in the mounting frame. See Figure 2.

Commissioning

Swegon recommends that the space behind the air diffuser 
be used as a pressure chamber. Equip the connecting duct 
to the relevant pressure chamber with a type CRM meas-
urement and commissioning damper. If the air diffuser is 
used as an ALS commissioning damper, adjust the airflow 
by placing the manometer measuring tube directly against 
the centre hole in the diffuser face. See Figure 2.
Measurement accuracy and requirement on straight duct 
before the commisioning box, see Figure 2. The require-
ments of straigh duct depends on the type of disturbance 
before the commissioning box. Figure 2 shows a bend, a 
dimensional change and a T-piece. Other types of dis-
turbances requires at least 2xD straight (D = connection 
dimension) for measurement accuracy of ± 10% of the 
flow.

Maintenance

The air diffuser can be cleaned, if necessary, using luke-
warm water with dishwashing detergent added or by 
vacuum cleaning using a brush nozzle. See Figure 2.

Figure 2. Installation, Commissioning, Maintenance

Figur 1. DPG Installation principle.

k

p

q

k

p

q

=

k

p

q

=

(    )

2

q

 = flow reading l/s

p

 = current pressure reading (Pa)

k

 = commissioning factor

k-factor

0xD / ±5%

0xD / ±5%

2xD / ±10%