Page 6
3454.504.02
Version 1.7
2.2 Fixation of the starting block
To ensure proper functioning of the OSB11 starting block system,
fixation must be absolutely rigid.
2.3 Drilling and mounting of the OSB11
For fix cabling, a hole with Ø120 - 122mm at 570mm away from the pool's border must be
foreseen in order to provide space for the cables (the gauge has a hole of Ø120mm).
Put the drilling gauge (1) on the border of the swimming pool and mark the 4 Ø5 holes of the
gauge with a Ø5 drill.
Drill the 4 holes respectively with drills
5,
10 and
16mm (2).
Minimal depth: 90mm, maximal
depth: 95mm
.
As per instruction manual 3393.505 "Preparing the drillings", push the pegs M8 (3) in the
16 holes and put the OSB11 starting block on the 4 fixation points.
Fix the base with the 4 screws M8 x 40 (5) and the 4 washers M8 (4).
Figure 5 - Fixation of the OSB11