A-96.250.491 / 190121
AMI Deltacon DG
Installation
17
3.
Installation
3.1. Installation Checklist Monitors
On-site require
-
ments
100–127 VAC, 200–240 VAC (±10%), 50/60 Hz (±5%)
power outlet with ground connection and 2.6 kW
Sample line with sufficient sample flow and pressure (see
Installation
Mounting of Instrument Panel, p. 18
.
Connecting Sample and Waste, p. 18
Monitor: Sensors are already mounted.
Cation exchanger
Fill up cation exchanger bottle with high purity water.
Remove the empty bottle and install the cation exchanger bottle.
Electrical Wiring
Note:
Do not switch on the Instrument until all electrical
connections are made.
Connect all external devices like limit switches, current loops and
.)
.
Power-up
Open sample flow and wait until flow cell is completely filled.
Manually deaerate the cation exchanger bottle.
Switch on power.
Adjust sample flow.
Instrument
set-up
Program all parameters for the sensors (cell constant, temperature
correction, cable length, temperature compensation for specific
conductivity).
If required activate calculations. Program all parameters for external
devices (interface, recorders, etc.).
Program all parameters for instrument operation (limits, alarms).
Program display screens.
Degasser
The instrument is delivered with the degassing unit switched off. To
switch the unit on, follow the instruction in chapter 4,
Run-in period
Let the instrument run continuously for 1 h. This is valid for rinsed
cation exchanger resin (nuclear grade) delivered by Swan.
If you do not use rinsed cation exchanger resin, the run-in period
may be much longer.