Installation
SUSPA ELS3 HeavyDuty - Installation Instruction
Page 40
Assembling the lifting elements with the top frame
Figure 24 Assembly of lifting elements of the 4-leg system with top frame
Fasten each lifting element with the help of the M6 screws supplied. Tool required: Size 5
Allen wrench
Figure 25 Size 5 Allen wrench
The M6x10 screws are used for mounting the fixing plates on the lifting elements. Four M6x10
screws are required for installing each fixing plate. The screws are inserted into the fixing
plate and fixed to the lifting element.
The three cross beams S and one cross beam E are fastened with the sleeves (24 pieces) and
the screws M6x25 (24 pieces) to the lifting elements as described in Figure 18.
Check the mounting screws of the lifting elements in order to ensure that they are fastened
securely to the HeavyDuty subframe. Take care not to over-tighten the lifting element
mounting screws (recommended tightening torque: max. 7 Nm).
Make sure that the electrical lines of each leg of the work surface can be laid without putting
them under mechanical tension by maintaining the permissible bending radius of 57 mm
(single) and 86 mm (multiple). The electrical wires to the lifting elements are each 1.2 m long.
8x
Screw
M6x10
24x
Sleeve
24x
Screw
M6x25
Cross beam E
Fixing plate
Cross beams S
Cross beam E