5.10. Battery Setup Page
To configure battery settings, click on the BATTERY icon and then on ‘Batt type’.
What this page displays:
Battery capacity in (Ah) – For non-BMS-batteries the range allowed is 0-2000Ah, while for
lithium-ion the inverter will user the capacity value of the BMS.
Max battery charge current (Amps).
Max battery discharge current (Amps), which should be 20% of the Ah rating for AGM only.
For Lithium, please refer to the battery manufacturer documentation. Note: This is a global
max. discharge current for both ‘grid-tied’ and ‘backup’ modes of operation and if the cur-
rent exceeds this value inverter will shut down with an overload fault.
TEMPCO settings - Temperature coefficient is the error introduced by a change in tempera-
ture.
What you can do from this page:
Use battery voltage for all settings (V).
Use battery SOC for all settings (%).
No battery: tick this box if no battery is connected to the system.
BMS setting.
Active battery - This feature will help recover a battery that is 100% discharged by slowly
changing from the solar array. Until the battery reaches a point where it can change normally.
Summary of Contents for SUNSYNK-8K-SG01LP1
Page 9: ...2 1 Product Size Page 9 Hybrid Inverter Installer Manual Inverter Size...
Page 16: ...Page 16 Hybrid Inverter Installer Manual 4 5 Function Port Definition...
Page 20: ...Page 20 Hybrid Inverter Installer Manual...
Page 22: ...Page 22 Hybrid Inverter Installer Manual 4 9 1 Recommended AC Surge Protector...
Page 28: ...Page 28 Hybrid Inverter Installer Manual 4 13 Wiring System for Inverter...
Page 29: ...Page 29 Hybrid Inverter Installer Manual...
Page 34: ...03 02 01 Page 34 Hybrid Inverter Installer Manual...
Page 37: ...Page 37 Hybrid Inverter Installer Manual 4 19 2 Connected to a Generator 03 02 01...